MGII and MG2T GAS FRYER
SERVICE
L22-236 Rev. 2 (06/11)
33
21. On full tanks, the slide the probe through the
ears of the bulb clamp, and then tighten clamp
to tapping pad with high limit bulb secured
beneath the clamp.
22. On full tanks, tighten the probe ferrule nut
using a 7/16” wrench.
23. Tighten the capillary ferrule nut using a 5/16”:
open-end wrench. Do not overtighten the
ferrule nut, as it will shear capillary tubing. ¼
turn beyond hand tight should provide
sufficient sealing.
24. For split tanks, repeat steps 17 – 20 and 23 for
the other tank half.
5.4.7. Tank
Installation
1. Install tank assembly into cabinet.
2. Attach tank to cabinet using 5/16” hex bit to
install the 4 mounting screws at the front of the
cabinet.
3. Install 2 mounting screws securing tank to
cabinet rear.
4. Apply a bead of food safe silicone sealant to
the seam(s) between adjacent tanks.
WARNING! SHUT OFF APPLIANCE AND DISCONNECT ALL POWER
CONNECTIONS PRIOR TO STARTING ANY SERVICE WORK