Petit Auto Wash Inc.
360-t Installation Manual
www.PetitAutoWash.com
P a g e
|
21
Accutrac 360-t Tunnel
Wired to Tunnel Controller Outputs:
-Input #1025
: 360 Start
(Extend & Enable) Signal (“On” whenever vehicle is in the 360)
-Input #1026
: Start Top HP Pump & Oscillator
-Input #1027
: Start Side HP Pump & Oscillator
-Input #1030 (Optional):
Rear Obstacle Avoidance Signal (Allows an operator to selectively add an
adjustable length to the rear of a car to avoid potential obstacles. See:
360-t Start-up Manual, Section 3.5: Set Timers & Miscellaneous Features.
Wired to either the Tunnel Controller Outputs or a remote button box.
-Input #1028 (Optional):
Remote Machine Reset
2.2.
25HP Variable Frequency Drive Panel:
Caution: Never drill holes in top of Control Panel. Use bottom or side entry only
Wall mount the panel using the supplied mounting feet. Electrician to provide (2) separate current
limiting Circuit Breakers (or equivalent) & wire, sized for the 25 HP motors, to the VFD Panel and from
the VFD Panel to both 25 HP motors. (2) Cat-5 Ethernet cables and (2) 18 AWG wires for the HP enable
circuit are required from the Control Panel to the VFD Panel.
2.3.
25HP Pump Stations & Tall Vehicle Solenoid:
Notes:
When wiring the pump station, note that not all 3-phase motors are not wired the same. Refer
to the diagram on the inside of each motor junction box for correct wiring specifications.
Some installations may not use the Tall Vehicle nozzle and solenoid valve.
Caster wheel kits are available for transporting the pump stations.
Feed each pump station fill-
tank with a 1” hose capable of supplying 40gpm @ 40 psi.
Install 40gpm
flow restrictors in the water lines feeding both the Side and Top HP Pump Stations. Note that if the
incoming water pressure is below 40psi, you may need to upsize these restrictors. If, while all
equipment is running, the building’s water pressure drops excessively
you may need to add restrictors
to other equipment or possibly down size these restrictors. Call the factory for recommendations.
Mount the Tall Vehicle Solenoid manifold on the wall in a convenient place near the HP pump stations.
T.V. Solenoid is 24VAC. Run a 3-wire 18 AWG conductor from the solenoid to the 360-t Control Panel.
Terminate the signal wire on Output # 0012.
Run (1) ¾” hig
h pressure line from the Top Washer 25Hp Pump to the Tunnel E-Chain Bulkhead.
(See drawing in section 1.7)
Run (1) ¾” high pressure line from the Side (Spray Arm) 25Hp Pump to the
Tall Vehicle Solenoid
Manifold. From the T.V. Solenoid Manifold run
(1) 3/4” & (1) 1/2” high pressure line to
Tunnel E-Chain
Bulkhead.
Содержание Accutrac 360-t
Страница 1: ...2044 Wadsworth Rd Norton Ohio 44203 www PetitAutoWash com Rev 8 18 360 t Tunnel Installation Manual...
Страница 9: ...Petit Auto Wash Inc 360 t Installation Manual www PetitAutoWash com P a g e 9 Accutrac 360 t Tunnel...
Страница 10: ...Petit Auto Wash Inc 360 t Installation Manual www PetitAutoWash com P a g e 10 Accutrac 360 t Tunnel...
Страница 15: ...Petit Auto Wash Inc 360 t Installation Manual www PetitAutoWash com P a g e 15 Accutrac 360 t Tunnel...
Страница 16: ...Petit Auto Wash Inc 360 t Installation Manual www PetitAutoWash com P a g e 16 Accutrac 360 t Tunnel...
Страница 29: ...Petit Auto Wash Inc 360 t Installation Manual www PetitAutoWash com P a g e 29 Accutrac 360 t Tunnel...