Assembly and Operation Manual
3. Install power supply unit in accordance with its operation manual.
Figure 10. Mounting hole layout
4. If it is necessary to lay power cables (13) and control cables (14) under the floor, prepare an
electrical conduit in the floor in the zone where cables are inserted into the gate post. The zone
positioning is given in Fig. 10.
5. Install anchors in the drilled holes in the floor, so that their sleeves would not obtrude out of the
floor surface.
6. Lay power cable and route the cable inside electrical conduit towards cable insertion zone. Pull
cables inside the fixed base (1) to the length appropriate for following installation on the control
board (6).
Attention!
Install and fix the gate post only when all cables are laid inside electrical conduit and the
gate post. Be careful until the post is not fixed, prevent it from falling down.
7. Install the gate post on anchors (9). Put it vertically by using a lever. Mounting pads may be
used. Vertical deviation shall not exceed 0.5º in two planes.
8. Remove the metal ring (5). Put a washer (11) on each anchor and fix the gate post with three
M10 nuts (10).
9. Connect power cable and control cable to
XT1
and
XT2
terminal blocks of the control board (6).
Put cables as shown in Fig. 3.
10. If needed, connect
Fire Alarm
emergency unlocking device. If the device is not connected, a
wire jumper shall be installed on
Fire Alarm
and
GND
contacts on
XT2
terminal block.
11. If it is necessary, connect external indicators to
XT1.2
and
XT1.3
terminal blocks.
12. If it is necessary, change the position of jumpers on the control board.
13. Mount the glass panel according to Fig. 12. Fix the panel (6) on the rotary support (7) with
elements (1) – (5).
Attention!
Be careful while mounting the glass panel, prevent it from falling and hitting by metal
elements of the post. Due to the significant weight of the panel, it is recommended to put a
support under it during the assembly.
14. Install the metal ring (5). Put the gate housing (2) on the post moving it alongside the post axis
till it stops.
15. Install the cover (3) on the top having unscrewed the bolts (8) using SW 1.5 Allen wrench. Fix
the cover with the bolts.
When the installation is finished turn the gate on and test its operation in accordance with