WMD-06 Motorized electromechanical swing gate
8
ASSEMBLY AND INSTALLATION
Observe safety requirements given in the Section 7.1 during installation.
8.1 General recommendations
Proper installation is crucial to performance and serviceability of the swing gate. We advise you to
study this Manual before installation work and follow the instructions to the latter.
We recommend:
to mount the swing gate on a steady concrete foundation (grade 400 or higher), stone or
similar foundations of at least 150 mm thick.
to make sure the mounting foundation is horizontal and steady, so that all the mount points
lie in the same plane;
to employ reinforcing elements 450×450×200 mm, when installing on a less steady
foundation.
8.2 Tools and equipment required for installation
Use the following tools for the installation works:
1.2÷1.5kW hammer drill;
Ø16 mm hard-alloy drill bits for anchor bolts sleeves;
Phillips head screwdriver No.1;
SW1.5 Allen wrench;
S17 open-end wrench;
hobby
knife;
level;
measuring tape 2 m.
Note:
The use of different tools is acceptable on condition that they do not reduce the quality of
installation works.
8.3 Appropriate cable length
Maximum acceptable length of RC panel / ACS controller cable .............................................. 30
m
Maximum acceptable length of power supply cable depends on its cross-section and shall be as
following:
for 1.5 mm
2
cross-section (AWG 15) ......................................................................max. 10 m
for 2.5 mm
2
cross-section (AWG 13) ......................................................................max. 20 m
8.4 Installation procedure
Attention!
The manufacturer shall not be liable for any damage caused in the result of improper
installation and declines any claims arising thereof in case if the installation is not in
compliance with the instructions provided in this Manual.
Item numbers in the installation sequence are given accordingly to Fig. 2, unless stated otherwise.
Wiring diagram is given in Fig. 11. Terminal blocks and jumpers positioning on the control board is
given in Fig. 3. Cables used for installation and their maximum lengths are set in Section 8.3.
Recommendations on surface preparation are given in Section 8.1. Follow this sequence during
gate installation:
1. Unpack the box with equipment, check carefully the delivery set according to Section 4.
Attention!
Don’t hold the gate by its cover (3) while moving it.
2. Mark and prepare the mounting holes in the floor as per Fig. 10 for anchors (9) to install the
gate post (If necessary, use the supplied template). Use Ø16 mm hard-alloy drill for hole
preparation. Drilling depth is 60 mm.
13