Appendix B (Continued)
Part Number: 5000423 & 2000930
Step 2.
Center Strut assembly between Bases at
required install location. With a felt marker or other
means
Mark
location of Roof Attachment in center slot
of U-bracket EZ.
Install
Roof Attachment per
manufacturer instructions.
Note:
Image shows roof markings at low edge of
module, process is the same for all MA installation
locations.
ALERT:
See Sheet Title:
Ballast Layout
–
XX
in the
Racking Construction Set for installation locations of
Mechanical Attachments on each individual project.
Torque
Clip
Torque Clip is fitted over the pilot
holes on the Base. MA Strut is then
aligned with the Torque Clip and Pilot
hole before being secured by an M6
Bolt.
Roof
markings
Step 3.
Install U-bracket EZ to MA Attachment using 3/8
”
nut
provided and tighten. Install torque clips onto the Bases and
align with pilot holes. Place MA Strut in center of U-Bracket
EZ and align slots with torque clips. Tighten remaining
connections as shown.
MA Struts
may be installed in several possible array
locations.
1. Low Edge Installation
2. High Edge Installation
3. Interior Installation
Tip: Tighten M6 Bolt Connections before tightening 3/8
”
connections to Roof Attachment.
1
2
3