Palax Power 100S
Translation
1-2017
20
Figs. 12 and 13
2. Fix the bracket (Fig. 13) that is located under the frame pipe to the M12 lock bolts. 2
pcs. of M12 Nyloc-nuts and 2 pcs. of 12 mm washers are required for the attach-
ment. Do not tighten.
3. Put the toplink lug in place, and insert the bolts.
4. Position the lug so that its distance from the PTO shaft’s centre-line is suitable for
the tractor (Fig. 14).
5. After this, tighten the M12 nuts, which were left loose at stage 6.
Figs. 14 and 15
Always hitch the machine to the three-point linkage of the tractor by the lug that is in-
stalled in the machine (Fig. 15).
A suitable power take-off shaft is, for example, BONDIOLI A 143 or WALTERSCHEID
W 2300.
No safety clutch is required for the PTO shaft.