SECTION 4 - MACHINE OPERATION
4-20
31215036
4.9
SHUT DOWN AND PARK
The preferred procedures to shut down and park the machine are
as follows:
1.
Drive machine to a reasonably well protected area.
2.
Ensure boom is fully retracted and lowered over rear axle.
3.
Shut down Emergency Stop at Platform Controls.
4.
Shut down Emergency Stop at Ground Controls. Position
Platform/Ground Select switch to center Off (center posi
-
tion).
5.
If necessary, cover Platform Controls to protect instruction
placards, warning decals, and operating controls from hos
-
tile environment.
IF PARKING A MEWP WITH THE BOOM ELEVATED IN AN EFFORT TO CONSERVE SPACE,
BOOMS MAY BE ELEVATED, BUT SHALL NOT BE EXTENDED. IT IS THE OPERATOR’S
RESPONSIBILITY TO ENSURE ALL SAFETY PRECAUTIONS IN SECTION 1 OF THIS MAN
-
UAL ARE FOLLOWED FOR EACH UNIQUE SITUATION.
4.10 AUXILIARY POWER
WHEN OPERATING ON AUXILIARY POWER, DO NOT OPERATE MORE THAN ONE FUNC
-
TION AT A TIME. (SIMULTANEOUS OPERATION CAN OVERLOAD THE 12-VOLT AUXIL
-
IARY PUMP MOTOR.)
A toggle type auxiliary power control switch is located on the
platform control station and another is located on the ground
control station. Operation of either switch turns on the electri
-
cally driven auxiliary hydraulic pump. This should be used in case
of failure of the main power plant. The auxiliary pump will oper
-
ate Boom Lift, Telescope, Jib, and Swing. To activate auxiliary
power: