CHAPTER 5 - Installation
CAUTION
All external power supply connections must be performed by the customer/buyer's personnel in the installation stage.
CAUTION
It is the customer's responsibility to ensure that the ground/surface can withstand the machine's overall static/dynamic load
(base, etc.).
The static load is provided in chapter 2.
The dynamic load should be considered as 10% greater than the static load.
CAUTION
For operating environmental conditions, refer to chapter 4 which sets out the features that the installation premises must have.
5.3.2
PROFESSIONAL PROFILES AND MANDATORY PPE
Below is a list of professional profi les and related PPE required for the installation stage.
Personal protection equipment set out under paragraph 1.9
5.3.3
CHOICE OF PREMISES AND ASSESSMENT OF INSTALLATION REQUIREMENTS
The area for machine installation and use must be suffi ciently wide to comply with:
•
operating spaces
•
transit ways
•
escape routes.
However, it is the customer's unequivocal responsibility to inspect the fi nal installation in compliance with applicable statutory requirements.
The ground/surface of the selected installation and use site must be even, level and conforming to the application specifi cations, as well as be able to
withstand the machine's weight specifi cations as per the provided static and dynamic loads.
Minimum space requirements according to the overall dimensions provided must be made available in order to handle/place the machine.
It is the buyer/customer's unequivocal responsibility, according to the risk assessment carried out based on the complete machine's intended fi nal use,
to assess the minimum space requirements for all activities such as maintenance, connection, inspection as well as any transit areas, escape routes,
etc. in compliance with applicable regulations and laws in the installation site and country of use.
The minimum safety distances from walls, the ceiling and any machine or site encumbrances must be taken into account by the customer, to perform
inspections and/or maintenance operations on the machine.
NOTE
The dimensions of the machine and related components are provided in chapter 2.4.2.
The supply consists of a load bearing structure (base) on which the machine is constructed.
Machine confi guration upon Ex Works delivery.
Please refer to chapter 2 for placement of the machine and its components and relevant minimum distances to be complied with. At any event, suitable
operating space should be left between and around components to grant convenient access for maintenance activities.
The Manufacturer requires maintenance space around the base of at least 2,000 mm / 78.74 in
5.3.4
LOADING, UNLOADING, LIFTING AND HANDLING PROCEDURES
Loading and unloading the machine on to and from a means of transport always involves potential risks, that is why IT IS INDISPENSABLE TO PAY
THE UTMOST ATTENTION.
Always block the wheels of the trailer and place blocks underneath both ramps used to load or unload the machine.
Always use ramps of adequate strength that are able to withstand the weight of the machine.
Ensure the ramps are long enough to provide safe loading and unloading grade (less than 8.5°) and ensure their width is adequate for the wheels of
the machine (minimum ramp width should be twice the width of a wheel).
Ensure the ramps are correctly placed and securely fastened to the vehicle the machine is to be transported with and that they are aligned at the same
level and cannot move or slip while the machine is loaded or unloaded.
Ensure the surfaces of the ramps are clean and free from grease, oil, ice and loose materials.