MOUNTING LIFTING COLUMNS TO FLOOR
Post 1 will have the Power Unit Mounting Bracket.
Mount
Lift Column 1 on the passenger side of the vehicle.
Determine desired location in bay for
Lift Column 1.
Allowing ample room
for Lift width and Lift Column 2 to be installed. Make sure there will
not be any obstructions within 6” of any post. Allow at least
Stand
Lift Column 1 in upright position.
Using holes in the Post Baseplate as a guide.
Drill Holes in concrete floor for a 5 ½” long ¾” diameter
Heavy Duty Anchor Bolt.
The depth of the holes should be ¼” deeper than the length of the
Anchor Bolt.
The Lift is supported only by the anchors in the floor. DO NOT install on
unstable surfaces such as asphalt. Minimum 3500psi concrete thickness 4”
Clean holes with
compressed air.
Insert eight (8) Anchor Bolts in Post 1 and tighten to
the
Anchor Bolt manufacturers’ recommended torque.
If Anchors do not tighten to 150 ft-lbs. installation torque, replace
concrete under each post base with a 4’x4’x8” thick 3500 PSI
minimum concrete pad.
Confirm that
Mounting Baseplates are square on centerline.
Install
Cables before securing Lift Column 2 to the floor.
Place the Overhead Telescope Assembly on top of the Posts.
Assure
Mounting Baseplates are level to each other.
Use
shims and non-shrink grout under unsupported areas of each Baseplate as needed.
Confirm that
Lift Columns are plumb.
Drill
holes for Lift Column 2 as described above and secure.
Fasten Lift Column 2 with eight (8) Anchor Bolts to the floor.
Remove the Overhead Telescope Assembly to install Cables.
Post 1 with Power Unit
Mounting Bracket
Post Base Plate
Overhead Telescope
Assembly
Mounting
Base Plate