Boiler Location
│
FTV I&O Manual
8
Figure 3-1 Closet Installation, Minimum Clearances
Ventilation Air Openings are
not required if the boiler area
meets
the
Recommended
Clearances listed in Table 3-1.
Top ventilation
opening M
ax. 6”
below ceiling / top
Ventilation air opening
1in
2
per 1000 Btu/hr,
min. 100in
2
Removable surface /
closet door
Ventilation air opening
1in
2
per 1000 Btu/hr,
min. 100in
2
Bottom ventilation
opening
Max. 6”
above floor / bottom
Sides = 4”
Top = 12”
Bottom = 9
”
Min. 1” clearance
for hot water and
vent pipes
Front = 6”
(if removable)