BREWER UNIT CLEANING CYCLE 

 

As well as manual cleaning through setting in the “Maintenance” menu, anyway performed without 

“Serving”, an automatic cleaning cycle can be set. 

After a selection, if a new “Serving” is not detected within 20 seconds, a cleaning cycle is carried out and the 

vending machine will be out of service for approximately 60 seconds. 

Manual cleaning must be carried out every time new “Servings” are loaded; it is however advisable to leave 
the automatic cycle control set at all times.

 

 
CHECKING AND ADJUSTING THE COFFEE DISPENSING PARAMETER SETTINGS 

 

In order to get the best possible quality for the dispensed products, the vending machine was adjusted to 

the optimum setting at the factory; however in relation to the products used it is advisable to check the 
following points: 

The water dose, which must be between 35 and 40 cc. 

The coffee dispensing temperature, which must be between 78° e 85° C. 
The pump by-pass valve setting, adjusted to 10 bar by default. 
The dispensing time, which must be between 18 and 20 seconds, considering that a longer time (with the same water 
dose) could to clog filters, and a shorter time could alter the by-pass setting towards a higher pressure, and lead to 

poorer dispensing quality. 
 

STANDARD SETTINGS 
 

By default the vending machine is adjusted at the factory as follows: 

Coffee temperature at the spout, 78-85° C 

Instant boiler temperature, 78-82° C 

Dispensing time, 18 to 20 seconds 

Coffee water dose, 35 to 40 cc 

 
ADJUSTING THE INSTANT BOILER WATER TEMPERATURE 

 

The instant boiler has a dual function: it provides hot water for all instant products by means of its two-way 

solenoid valve. 

It pre-heats water for the flow-through boiler to avoid the scaling problem typical of such type of boiler. 

It is therefore important to have an optimum setting, as a temperature change affects also the final 

temperature of the coffee. 

To change such temperature the special trimmer on the machine board must be used. 

Considering that:  
Tightening (clockwise) will increase the temperature 

Loosening (anticlockwise) will decrease the temperature 

Each complete turn correspond to +/- 0.5° C change 

 
BOILER OVERHEATING PROTECTIONS 

 

The boilers are fitted with safety overheating protections. 

The espresso boiler is fitted with two thermo-fuses located above it and sheathed in a special silicone tube. 

In the event of failure that could cause boiler overheating, the two thermo-fuses melt, thus disconnecting 

the power from the heating element.  

After the occurrence of such melting, the problem that caused the malfunction must be identified, corrected 
and BOTH THERMO-FUSES MUST BE REPLACED with identical ones or having the same characteristics. 

Fuses must never be replaced with others that are not approved by the manufacturer, otherwise hazard 

conditions could be created and the manufacturer declines all responsibility. 

The instant boiler is fitted with manual reset overheating protection; therefore after having identified and 

corrected the cause it is sufficient to press the upper red button to restore the initial conditions. 

 

 
 

Содержание BRIO "Easy Serving Espresso"

Страница 1: ...NUAL Brio Easy serving Espresso Manual Brio ESE 1 17 by AFTER SALES SERVICE Hot Cold Brio Easy Serving Espresso BASIC TECHNICAL MANUAL THE CONTENTS OF THIS DOCUMENT ARE INTENDED FOR NECTA S AFTER SALE...

Страница 2: ...r open Table of Contents 1 2 3 4 5 6 7 8 9 Layout Electrical systems and board connections Air break Boilers Pumps and by pass Coffee brewer unit Mixer Unit Powder and water dose tables Trouble shooti...

Страница 3: ...alve 8 Flow through Espresso boiler 2 Mechanical filter for impurities 9 Flow through coil 3 Air break 10 Three way solenoid valve 1 4 Volumetric counter 11 Three way solenoid valve 2 5 Vibration pump...

Страница 4: ...me compartment and controlling the flow through espresso boiler see photo Two other boards are installed 1 The display board which processes the information from the CPU board and converts it into rea...

Страница 5: ...e serial interface 9 Front validator connector 10 Jp1 11 Coin return lamp 12 NOT USED 13 MDB board power supply 14 MDB coin mechanism connector 15 Programming mode button CPU board component legend Re...

Страница 6: ...relief solenoid valve 2 K3 Instant drink solenoid valve 2 K4 Pump K5 Coffee brewer motor K6 Instant drink solenoid valve 2 K7 Pod strip Serving drive motor K8 Mixer motor 1 K9 Doser device 3 K10 Dose...

Страница 7: ...upporting 512 Kb and 1 Mb EPROMs by setting Jumpers JS3 and JS4 For the different configurations see the following tables LANGUAGE CONFIGURATION LANGUAGE Minidip Italian French Spanish 6 OFF ON OFF 7...

Страница 8: ...t and microswitch When a coffee selection is made after positioning the pod in the brewing chamber the pressure boiler two way solenoid valves is opened and the vibration pump is started for a length...

Страница 9: ...the coffee pod and thus ensuring better dispensed product quality To ensure greater pump reliability and better tightness against the pressure a check valve was added at the boiler inlet this way no...

Страница 10: ...p to 95 100 C ideal for espresso coffee The brewing chamber is kept hot at the same temperature of the flow through boiler The pump delivers the programmed amount of water that is accurately computed...

Страница 11: ...to the brewer after removing the keys 1 front and if necessary back this way access is gained to the lower filter using a screwdriver lift the edge until removed completely Clean and descale using su...

Страница 12: ...e system is adjusted to the optimum setting at the factory however in the event of disassembly for cleaning and or replacing filters and gaskets it may be necessary to readjust the settings in this ca...

Страница 13: ...Dispensing time 18 to 20 seconds Coffee water dose 35 to 40 cc ADJUSTING THE INSTANT BOILER WATER TEMPERATURE The instant boiler has a dual function it provides hot water for all instant products by m...

Страница 14: ...te 7 5 gr Instant Coffee Optional Time Quantity 1 3 gr 22 55 cdv 40c c 7 5 gr Chocolate Time Quantity 32 116 cdv 90 c c 23 28 gr Instant tea Time Quantity 32 116 cdv 90 c c 12 14 gr Milk Time Quantity...

Страница 15: ...e Overheating protection triggered For the espresso boiler melted thermo fuse The vending machine is locked if the set temperature is not reached within 10 minutes Check the correct operation of the h...

Страница 16: ...failure If the ere is no communication between coin mechanism and CPU board for 30 seconds for serial coin mechanisms only Check for correct connection and configuration of the minidips if all correct...

Страница 17: ...TECHNICAL MANUAL Brio Easy serving Espresso Manual Brio ESE 17 17 9 WIRING DIAGRAMS...

Отзывы: