Installing the Conveyor
Parts Needed:
Spacers
Conveyor
4’
: 30mm (2), 60mm (2)
Conveyor
7’
Left & Right: 30mm (4)
M8 Button Head Bolt (8)
1.
Locate the Pivot Thumb Screw pre-installed on each Mount
Bracket. Loosen the Pivot Thumb Screw
do not remove
and
reposition the Pivot Bracket to the fully closed position. The Pivot
Bracket should be as close to the machine as the adjustment slots
will allow. Tighten the Pivot Thumb Screw to lock the Pivot Bracket
into position.
▪
CAUTION
–
Ensure that the Pivot Thumb Screw is hand
tight prior to installing the conveyor. Failure to do so could
allow for the conveyor to pivot possibly dropping the
assembly and causing injury.
2.
Locate the four Conveyor Mount Tabs, two are on each Mounting
Bracket Assembly. Also locate the mounting hardware: four 30
mm Spacers, and eight M8 Button Head Bolts. The 30mm M8 T Nuts are installed in the Conveyor
Frame Side Channel.
3.
Conveyors will have multiple M8 T Nuts and Studs pre-
installed within the Conveyor Frame Channel. M8 T
Nuts have been taped in place;
Do not remove tape
until later.
Identify the M8 T Nuts associated with the Conveyor
4’
or Conveyor
7’
Mounting tabs, these will be 30mm and
60mm M8 T Nuts within the Conveyor Frame Channel
these have two threaded holes in each. The operator side of all conveyors will have one additional
60mm M8 T Nut, this will always be on the opposite side of the drive shaft.
Four of the M8 T Nuts installed within the Conveyor Frame Channel will align with the Conveyor Mount
Tabs on each conveyor model as shown below:
Conveyor 4’
- Right