![Munch Machine CON-1204R Скачать руководство пользователя страница 11](http://html1.mh-extra.com/html/munch-machine/con-1204r/con-1204r_operators-manual_1856472011.webp)
11
Shift the conveyor left or right to align the Conveyor Mount
Tabs with the four outermost taped 30mm or 60mm T Nuts
within the Conveyor Frame Channel. Remove tape holding T
Nuts in place.
▪
CAUTION
–
Continue to support conveyor until all
fasteners are installed. Failure to do so could allow for
the conveyor to fall causing injury.
Two M8 Button Head Bolts and one Spacer (30mm or 60mm)
matching the width of the corresponding Conveyor Mount
Tab will be installed. The Bolts will pass through the Conveyor
Mount Tab, into the spacer then thread into the T Nut
Installed in the Conveyor Frame Channel -
Lightly Tighten
.
*On the Conveyor
7’
–
Right and Left configurations, only three of the Conveyor Mount Tabs
will be accessible to install the fasteners. Installation of these fasteners happen in upcoming
steps.
Installing the Shield Assembly
Parts Needed:
Shield Assembly
1.
Loosen but
do not remove
the three Thumb Screws (female) that are installed on the Conveyor Frame.
The Fourth attachment point for the Shield Assembly is a Mount Peg, no adjustment is needed for this
part.
2.
Loosen the Thumb Screws located on the Pivot Bracket (Mounting Bracket Assembly). Holding the
conveyor frame squarely pull the entire conveyor away from the machine. Pull equally from the middle
of the conveyor to prevent binding. Ensure that both Thumb Screw Bushings contact the forward most
part of the Pivot Bracket Channel.
Do not let the conveyor tilt
, retighten the Pivot Bracket Thumb
Screws with the Conveyor in the horizontal position.
▪
CAUTION
–
Ensure that the Pivot Thumb Screw is tight securing the assembly from Pivoting.
Failure to do so could allow for the conveyor to pivot possibly dropping the assembly and
causing injury.