7 Maintenance

Maschinenfabrik Reinhausen GmbH 2020

53

5993419/02 EN

VACUTAP

®

 VMS

®

4. Once the gas has been discharged and insulating fluid is flowing out of

the air-vent valve, close the air-vent valve.

5. Close the stop-cock between the oil conservator and on-load tap-changer.

6. Open air-vent valve E1 again and extract approximately 5–10 liters of in-

sulating fluid via the pipe connection S until the area under the on-load
tap-changer head cover is free of insulating fluid.

7. Remove the screws and washers from the on-load tap-changer head

cover.

Figure 26: On-load tap-changer head cover

8. Remove on-load tap-changer head cover.

Figure 27: On-load tap-changer head cover

9. Extract insulating fluid via pipe connection S.

10. Open the stop-cock between oil conservator and on-load tap-changer.

ð

The insulating fluid flows out of the oil conservator into the oil com-
partment.

11. Extract insulating fluid via pipe connection S.

Содержание VACUTAP VMS

Страница 1: ...On load tap changer VACUTAP VMS Operating Instructions 5993419 02 EN Selector size C ...

Страница 2: ... for compensation All rights reserved in the event of the granting of patents utility models or designs The product may have been altered since this document was published We reserve the right to change the technical data design and scope of supply Generally the information provided and agreements made when processing the individual quotations and orders are binding The original operating instruct...

Страница 3: ...protective equipment 14 3 Product description 15 3 1 On load tap changer 15 3 1 1 Function description 15 3 1 2 Setup models 16 3 1 3 Nameplate and serial number 18 3 1 4 Protective devices 18 3 2 Drive shaft 25 3 2 1 Function description 25 3 2 2 Design versions 26 4 Commissioning 31 4 1 Commissioning transformer at operating site 31 4 1 1 Filling the oil compartment of the on load tap changer wi...

Страница 4: ...ng on load tap changer to adjustment position 50 7 3 2 Removing horizontal drive shaft 50 7 3 3 Emptying the oil compartment and oil conservator 52 7 3 4 Filling the oil compartment and oil conservator with fresh insulating fluid 54 7 3 5 Installing horizontal drive shaft 56 7 3 6 Centering on load tap changer and motor drive unit 57 7 4 Performing DC resistance measurement on transformer 57 8 Tec...

Страница 5: ...N VACUTAP VMS 9 Drawings 66 9 1 Dimensional drawings 66 9 1 1 746230 67 9 2 Selector 69 9 2 1 890477 70 9 3 On load tap changer head 71 9 3 1 896762 72 9 3 2 893899 73 9 3 3 766161 74 9 3 4 892916 75 9 4 Tools 76 9 5 Additional drawings 76 9 5 1 898012 77 9 5 2 898026 78 ...

Страница 6: ...sonnel 1 1 Manufacturer The product is manufactured by Maschinenfabrik Reinhausen GmbH Falkensteinstraße 8 93059 Regensburg Tel 49 9 41 40 90 0 E mail sales reinhausen com Further information on the product and copies of this technical file are avail able from this address if required 1 2 Completeness This technical file is incomplete without the supporting documents The following documents are co...

Страница 7: ...s refer to a particular part within a section These warn ings apply to smaller units of information than the warnings relating to sec tions Embedded warnings use the following format DANGER Instruction for avoiding a dangerous situation 1 4 1 3 Signal words and pictograms The following signal words are used Signal word Definition DANGER Indicates a hazardous situation which if not avoided will res...

Страница 8: ...Warning of danger of crushing Table 2 Pictograms used in warning notices 1 4 2 Information system Information is designed to simplify and improve understanding of particular procedures In this technical file it is laid out as follows Important information 1 4 3 Instruction system This technical file contains single step and multi step instructions Single step instructions Instructions which consis...

Страница 9: ...ptional Step 1 of 1 ð Result of step optional ð Result of action optional Multi step instructions Instructions which consist of several process steps are structured as follows Aim of action ü Requirements optional 1 Step 1 ð Result of step optional 2 Step 2 ð Result of step optional ð Result of action optional ...

Страница 10: ...from delivery installation and operation to removal and disposal The following is considered appropriate use Use the product only with the transformer motor drive unit specified in the order The serial numbers of on load tap changer and on load tap changer ac cessories drive drive shaft bevel gear protective relay etc must match if the on load tap changer and on load tap changer accessories are su...

Страница 11: ...s Higher voltages may occur due to transformer overexcitation following load shedding for example Operations outside of the permitted operating conditions can lead to injury to persons and damage to the product Prevent any such operations outside of the permitted operating conditions by taking suitable measures 2 3 Fundamental safety instructions To prevent accidents malfunctions and damage as wel...

Страница 12: ...work on the product in ar eas where a risk of explosion is present Safety markings Warning signs and safety information plates are safety markings on the product They are an important aspect of the safety concept Observe all safety markings on the product Make sure all safety markings on the product remain intact and legible Replace safety markings that are damaged or missing Ambient conditions To...

Страница 13: ...sonnel are sufficiently quali fied Electrically skilled person The electrically skilled person has a technical qualification and therefore has the required knowledge and experience and is also conversant with the ap plicable standards and regulations The electrically skilled person is also pro ficient in the following Can identify potential dangers independently and is able to avoid them Is able t...

Страница 14: ...aintenance 2 5 Personal protective equipment Personal protective equipment must be worn during work to minimize risks to health Always wear the personal protective equipment required for the job at hand Never wear damaged personal protective equipment Observe information about personal protective equipment provided in the work area Protective clothing Close fitting work clothing with a low tearing...

Страница 15: ...e power transmis sion grid For this purpose on load tap changers are fitted in transformers and connected to the active part of the transformer A motor drive unit which receives a control impulse e g from a voltage reg ulator changes the operating position of the on load tap changer as a result of which the transformer s transmission ratio is adapted to the prevailing op erating requirements Figur...

Страница 16: ...n components of the on load tap changer You will find a detailed drawing of the on load tap changer in the Drawings Section 9 Page 66 section Figure 2 On load tap changer 1 Rupture disk 2 On load tap changer head cover 3 On load tap changer head 4 Oil compartment 5 Selector 6 Change over selector 7 Pipe bend 8 Upper gear unit 3 1 2 1 Pipe connections The on load tap changer head features 4 pipe co...

Страница 17: ...be interchanged Pipe connection S The pipe bend on pipe connection S features a vent screw and can be con nected to a pipe that ends with a drain valve on the side of the transformer tank at operating height If the on load tap changer is fitted with an oil suc tion pipe the on load tap changer can be completely emptied via pipe con nection S Pipe connection R Pipe connection R is intended for atta...

Страница 18: ...y for drying filling with insulating fluid and transportation of the transformer 3 1 3 Nameplate and serial number The nameplate with serial number is on the on load tap changer head cover Figure 4 Nameplate The serial number can also be found on the selector Figure 5 Serial number 3 1 4 Protective devices The on load tap changer is equipped with the following protective devices ...

Страница 19: ...ry reed magnetic switch is thereby actuated the circuit breakers are tripped and the trans former is de energized The protective relay is a component of an on load tap changer filled with in sulating fluid and its properties conform to the respective applicable version of IEC publication 60214 1 Diverter switch operations at rated switching capacity or at permissible over load will not cause the p...

Страница 20: ... protective relay RS 2001 R has an extra inspection window on the rear View from above Figure 8 Protective relay RS 2001 1 Gasket 2 Potential tie in 3 Terminal box cover 4 Slotted head screw for potential tie in 5 OPERATION reset test button 6 Slotted head screw for protective cover 7 OFF test tripping test button 8 Cable gland 9 Protective cover 10 Dummy plug ...

Страница 21: ...s installed on the outside of the on load tap changer and is tripped by impermissible static and dynamic pressures in the on load tap changer oil compartment The pressure monitoring device uses a concept where a corrugated tube acts as a barometer together with a spring providing counter force This as sembly is mechanically linked to the sensor on the snap action switch The pressure increase activ...

Страница 22: ...res and characteristics of the pressure monitoring device comply with the respective applicable version of IEC publication 60214 1 Diverter switch operations at the rated switching capacity or permitted over load do not cause the pressure operated relay to trip The pressure operated relay responds to a pressure change and not to gas accumulation under the pressure operated relay Gas accumulation u...

Страница 23: ...2020 23 5993419 02 EN VACUTAP VMS The housing and the cover cap of the pressure monitoring device consist of lightweight corrosion resistant metal Figure 10 Snap action switch and pressure measuring element 1 Snap action switch 2 Pressure measuring element ...

Страница 24: ...onds to a defined overpressure in the oil compartment of the on load tap changer 3 1 4 4 Pressure relief device MPreC On request MR will supply a pre fitted MPreC pressure relief device in place of the rupture disk This device responds to a defined overpressure in the oil compartment of the on load tap changer The on load tap changer therefore meets the requirements of IEC 60214 1 regarding pressu...

Страница 25: ...s the mechanical connection between the drive and the on load tap changer de energized tap changer The bevel gear changes the direction from vertical to horizontal Accordingly the vertical drive shaft has to be mounted between drive and bevel gear and the horizontal drive shaft between bevel gear and on load tap changer or de energized tap changer ...

Страница 26: ...s of a square tube and is coupled at each end by two coupling brackets and one coupling bolt to the driving or driven shaft end of the device to be connected Figure 12 Components of the drive shaft 1 Bevel gear 2 Hose clip 3 Telescopic protective tube 4 Coupling bracket 5 Square tube 6 Coupling bolt 7 Adapter ring 8 Protective cover ...

Страница 27: ... shaft without cardan joint and without insulator standard version Configuration V 1 min Intermediate bearing Middle of hand crank middle of bevel gear maximum permissible axial offset 2 536 mm When the maximum value of 2472 mm is exceeded it is necessary to use an in termediate bearing V 1 2472 mm without in termediate bearing V 1 2472 mm with inter mediate bearing ...

Страница 28: ...e shaft without cardan joint and with insulator special model Configuration V 1 min Intermediate bearing Middle of hand crank middle of bevel gear maximum permissible axial offset 2 706 mm When the maximum value of 2472 mm is exceeded it is necessary to use an in termediate bearing V 1 2472 mm without in termediate bearing V 1 2472 mm with inter mediate bearing ...

Страница 29: ... VMS 3 2 2 3 Drive shaft with cardan joint and without insulator Figure 15 Drive shaft with cardan joint and without insulator special model Configuration V 1 min mm Intermediate bearing for mm Middle of hand crank middle of bevel gear maximum permissible axial offset 20 798 V 1 2564 ...

Страница 30: ...TAP VMS 3 2 2 4 Drive shaft with cardan joint and with insulator Figure 16 Drive shaft with cardan joint and with insulator special model Configuration V 1 min mm Intermediate bearing for mm Middle of hand crank middle of bevel gear maximum permissible axial offset 20 978 V 1 2772 ...

Страница 31: ...ty damage is highly probable Ensure that the on load tap changer is not overloaded Ensure use of the on load tap changer in accordance with section Ap propriate use Prevent operations outside of the permitted operating conditions by tak ing suitable measures 4 1 Commissioning transformer at operating site Before energizing the transformer check that the motor drive unit and pro tective devices are...

Страница 32: ... 3 Fill on load tap changer with new insulating fluid using one of the two free pipe connections of the on load tap changer head Figure 18 Pipe connections S and R 4 Take a sample of insulating fluid from the oil compartment 5 Record the temperature of the sample immediately after the sample is taken 6 Determine dielectric strength and water content at an insulating fluid tem perature of 20 C 5 C ...

Страница 33: ...ad tap changer head 1 Open all forward valves and return valves in the pipe system 2 Remove screw cap on air vent valve E1 on the on load tap changer head cover Figure 19 Screw cap 3 Use screwdriver to lift valve tappet on air vent valve E1 and bleed on load tap changer head Figure 20 Valve tappet 4 Seal air vent valve E1 with screw cap tightening torque 10 Nm ...

Страница 34: ...t screw and bleed suction pipe completely 3 Close vent screw 4 Seal vent screw with screw cap 4 1 3 Checking motor drive unit NOTICE Damage to the on load tap changer de energized tap changer Damage to the on load tap changer de energized tap changer due to actu ation of the on load tap changer de energized tap changer without insulat ing fluid Ensure that the selector de energized tap changer is ...

Страница 35: ...it and on load tap changer are correctly coupled and that the motor drive unit functions correctly Tests on the motor drive unit 1 Perform function checks as described in relevant MR operating instruc tions for motor drive unit 2 NOTICE An incorrectly coupled motor drive unit will lead to damage to the on load tap changer Undertake trial tap change operations across the entire range of settings En...

Страница 36: ...r and affix using the slotted head screw 16 Attach the terminal box cover and secure with screws 4 1 4 2 Checking protective relay RS 2004 ü Check that the protective relay is functioning correctly before commission ing the transformer 1 Ensure that the flap valve is in the OPERATION position 2 Leave the transformer s danger zone 3 Close the transformer s circuit breaker with isolating switches op...

Страница 37: ...act for falling below the minimum insulating fluid fill level in the on load tap changer s oil conservator is looped into the tripping cir cuit of the circuit breaker ü The protective relay and additional protective devices are looped into the circuit breaker s tripping circuit ü The motor drive unit and all protective devices are functioning correctly and are ready for use ü The oil compartment o...

Страница 38: ...rtment of Maschi nenfabrik Reinhausen GmbH immediately To operate the motor drive unit manually only use the hand crank mounted in the motor drive unit For information about fault rectification refer to the Fault elimination chap ter Normal operation During normal operation there is no need to operate the unit with the hand crank The hand crank is mainly required during installation and for tests ...

Страница 39: ...cuit will not be interrupted 4 NOTICE Damage to the on load tap changer due to tap change opera tion not being completed correctly Turn the hand crank in one direction until the pointer has fully circled the tap change indicator once and is again in the mid position of the area marked in gray on the tap change in dicator ð The tap change operation is complete 5 Remove the hand crank and return it ...

Страница 40: ...protective relay or other protective devices have been tripped Do not use the equipment again until you are sure there is no damage to the on load tap changer or transformer NOTICE Damage to motor drive unit Damage to the motor drive unit due to condensate in protective housing of motor drive unit Always keep protective housing of the motor drive unit tightly closed In the event of operation inter...

Страница 41: ...d tap changer head cover On load tap changer and transformer must be checked Depending on the cause of tripping take measurements carry out checks on the transformer Contact MR to check the on load tap changer Tripping of motor protective switch in motor drive unit See chapter Fault elimination in the operating instruc tions of the TAPMOTION ED motor drive unit Tripping of signaling contact that i...

Страница 42: ...rotective relay can deflagrate or explode and result in severe injury or death Wait 15 minutes after switching off the transformer before beginning fur ther work on the protective relay so that the gases can dissipate Ensure that there are no ignition sources such as naked flames hot sur faces or sparks e g caused by the build up of static charge in the imme diate surroundings and that none occur ...

Страница 43: ... not tripped due to an error in the tripping circuit also proceed as described below for RS 2004 If the flap valve is in the OFF position proceed as follows 1 Ensure that the transformer is not started up under any circumstances 2 Contact and inform Maschinenfabrik Reinhausen of the following ð Serial number of protective relay and on load tap changer ð What was the load of the transformer at the ...

Страница 44: ...ating position of on load tap changer 3 As a precaution block the motor drive unit by tripping the motor protective switch to prevent the on load tap changer from being actuated by remote control 4 Check the on load tap changer head cover If insulating fluid is leaking close the oil conservator stop valve immediately 5 Check whether the pressure monitoring device sensor is in the OFF posi tion or ...

Страница 45: ...n the network being carried out at the in stant of tripping ð Were overvoltages registered at the instant of tripping ð How high is the static pressure on the pressure relief device height dif ference between the oil level in the on load tap changer oil conservator and the pressure relief device 3 Take further action in agreement with Maschinenfabrik Reinhausen 6 2 3 Re commissioning the transform...

Страница 46: ...losive gases in the oil compartment of the on load tap changer trans former pipe system oil conservator and at the dehydrating breather open ing can deflagrate or explode and result in severe injury or death Ensure that there are no ignition sources such as naked flames hot sur faces or sparks e g caused by the build up of static charge in the trans former s immediate surroundings and that none oc...

Страница 47: ...lled in positions other than the neutral point of windings Class 2 in accordance with 60214 1 1 Take a sample of insulating fluid from the oil compartment 2 Record the temperature of the sample insulating fluid im mediately after the sample is taken 3 Determine dielectric strength and water content at an insu lating fluid temperature of 20 C 5 C The dielectric strength and water content must compl...

Страница 48: ...lowing maintenance intervals shall apply Interval Action after 300 000 switching operations mo tor drive unit counter reading Maintenance of the on load tap changer Contact the Maschinenfabrik Rein hausen GmbH Technical Service Sec tion 6 Page 40 for this after 600 000 switching operations mo tor drive unit counter reading Replacement of diverter switch insert Contact the Maschinenfabrik Rein haus...

Страница 49: ...ous injury as a result of a progressive short circuit for example Contact the Maschinenfabrik Reinhausen GmbH Technical Service de partment as soon as the MR monitoring system issues a maintenance warning In the event of failure or shutdown of the MR monitoring system observe the maintenance intervals as specified in the maintenance plan without the MR monitoring system If you are operating the on...

Страница 50: ...cified in the technical data 7 3 1 Moving on load tap changer to adjustment position 1 Make a note of the current operating position of the on load tap changer 2 Move the on load tap changer to the adjustment position The adjustment position is indicated in the on load tap changer connection diagram in cluded in delivery 7 3 2 Removing horizontal drive shaft NOTICE Damage to the on load tap change...

Страница 51: ...Maintenance Maschinenfabrik Reinhausen GmbH 2020 51 5993419 02 EN VACUTAP VMS 1 Loosen hose clips on protective cover of horizontal drive shaft remove protective cover Figure 23 Removing protective cover ...

Страница 52: ...re not to lose the coupling bolts Figure 25 Removing drive shaft 7 3 3 Emptying the oil compartment and oil conservator 1 Ensure that the stop cock between oil conservator and on load tap changer is open 2 Remove the screw cap on air vent valve E1 on the on load tap changer head cover 3 Use a screwdriver to lift the valve tappet on air vent valve E1 ð The gas under the on load tap changer head cov...

Страница 53: ...luid via the pipe connection S until the area under the on load tap changer head cover is free of insulating fluid 7 Remove the screws and washers from the on load tap changer head cover Figure 26 On load tap changer head cover 8 Remove on load tap changer head cover Figure 27 On load tap changer head cover 9 Extract insulating fluid via pipe connection S 10 Open the stop cock between oil conserva...

Страница 54: ...abrik Reinhausen GmbH s Technical Service department 1 Fill the oil compartment of the on load tap changer with fresh insulating fluid via the pipe connection S up to the level of the carrier plate 2 Insert the new o ring untwisted in the on load tap changer head cover 3 Check that the feather key is securely positioned in the adapter shaft Where necessary use Vaseline to secure the feather key ag...

Страница 55: ...on load tap changer head cover To do this remove screw cap and lift valve tap pet with a screwdriver 8 Seal air vent valve E1 with screw cap tightening torque 10 Nm 9 Remove screw cap from pipe connection S Figure 31 Pipe connection S 10 Open vent screw and bleed piping 11 Close vent screw 12 Seal vent screw with screw cap 13 Check the level in the oil conservator and top up with insulating fluid ...

Страница 56: ...s taken 17 Determine dielectric strength and water content at a sample temperature of 20 C 5 C The dielectric strength and water content must comply with the limit values specified in the technical data after maintenance 7 3 5 Installing horizontal drive shaft 1 Secure horizontal drive shaft between upper gear unit and bevel gear with coupling brackets and 4 or 6 screws Refer to the drive shaft op...

Страница 57: ...rdan shafts You will find a detailed description of how to fit the drive shaft in the MR op erating instructions Drive shaft 7 3 6 Centering on load tap changer and motor drive unit Center on load tap changer and motor drive unit as described in relevant MR operating instructions for motor drive unit 7 4 Performing DC resistance measurement on transformer The measured DC current is normally restri...

Страница 58: ...is interrupted when changing operating position or not Status of oil compart ment Without interruption in measured current With interruption mea sured current 0 A be fore change of operating position Oil compartment empty Maximum 10 A DC Maximum 50 A DC Oil compartment filled with insulating fluid Maximum 50 A DC Maximum 50 A DC Table 7 Maximum permitted measured currents when performing DC resist...

Страница 59: ...city PStN kVA 520 845 Rated frequency Hz 50 60 Table 8 Electrical data for VACUTAP VMS III selector size C 1 The maximum rated step voltage may be exceeded by 10 due to overexcitation of the transformer if the step capacity is limited to its rated value Mechanical data Number of operating positions Without change over selector maximum 18 With change over selector maximum 35 Number of equipped sect...

Страница 60: ...rture Weight approx 3 5 kg Oil flow speed of available types when tripping oil temperature 20 C 0 65 0 15 m s 1 20 0 20 m s 3 00 0 40 m s 4 80 0 60 m s Table 11 General technical data Tripping circuit The protective relay can be supplied with either a normally open NO or a normally closed NC dry reed magnetic switch see dimensional drawing supplied Other contact combinations are available as a spe...

Страница 61: ...test duration 1 minute Table 14 Dielectric strength Electrical data for normally open NO dry reed magnetic switch Electrical data DC switching capacity 1 2 W 250 W AC switching capacity 50 Hz 1 2 VA 400 VA Switching voltage AC DC 24 V 250 V Switched current AC DC 4 8 mA 2 A Table 15 Electrical data Switching capacity switching load on an off Minimum switched current AC DC low est voltage 50 mA at ...

Страница 62: ...ontact as tripping switch The protective relay can be supplied with a dry reed magnetic switch CO change over variant 3 see dimensional drawing supplied Electrical data for CO change over dry reed magnetic switch Electrical data DC switching capacity 1 2 W 150 W AC switching capacity 50 Hz 1 2 VA 200 VA Switching voltage AC DC 24 V 250 V Switched current AC DC 4 8 mA 1 A Table 19 Electrical data S...

Страница 63: ... supplied with several independent dry reed mag netic switches These can be designed as normally open NO or normally closed NC contacts and are electrically isolated see dimensional drawing supplied Electrical data for normally open NO and normally closed NC dry reed magnetic switch 8 4 Technical data for pressure monitoring device General technical data Setup Outdoor model Ambient temperature 40 ...

Страница 64: ...ar Snap action switch Connection terminals Lead connection 1 or 2 leads per terminal Ø 0 75 2 5 mm Contacts 1xNO normally open 1xNC normally closed Utilization category IEC 60947 5 1 AC 15 230 V 1 A DC 13 60 V 0 5 A Maximum continuous current 10 A Rated insulation voltage AC 2 5 kV min Table 22 General technical data ...

Страница 65: ...ured in accordance with IEC 60156 and water content measured in accordance with IEC 60814 of insulating fluids The values have been established based on IEC 60422 Limit values for insulating fluids in ac cordance with IEC 60296 Ud H2O When commissioning the transformer for the first time 60 kV 2 5 mm 12 ppm During operation 30 kV 2 5 mm 30 ppm After maintenance 50 kV 2 5 mm 15 ppm Table 23 Insulat...

Страница 66: ...9 Drawings Maschinenfabrik Reinhausen GmbH 2020 66 5993419 02 EN VACUTAP VMS 9 Drawings 9 1 Dimensional drawings ...

Страница 67: ...satz Alle Rechte für den Fall der Patent Gebrauchsmuster oder Designeintragung vorbehalten A1 PROTECTIVE RELAY SCREENINGS SEE 730336 WITHDRAWAL HEIGHT Y 1 1 29 O 73 O 19 75 11 O 1 1 1 1 72 5 kV 123 300 kV t 8 35 48 48 11 55 25a 25 29a 24 23 54 53 52 56 51 16 13 14 29c 21 38 31 33 33 39 32a 32 27 Z A A 22 A A 12 5 O 12 5 O 12 5 O 1 2 0 1 2 0 36 M 29b 28 29c 27 26 29a 15 15 24 25 25a 17 21 M Z 72 5 ...

Страница 68: ...R OIL COMPARTMENT VENT SCREW FOR SUCTION PIPE SELECTOR SUSPENSION SELECTOR GEAR TAP SELECTOR CHANGE OVER SELECTOR SELECTOR CONNECTION CONTACT SEE CORRESPONDING DIMENSION DRAWING CHANGE OVER SELECTOR CONNECTION CONTACT K OR O CHANGE OVER SELECTOR CONNECTION CONTACT OR SELECTOR CONNECTING LEAD 41 42 43 44 45 46 47 48 31 32 33 34 35 36 37 38 39 DIVERTER SWITCH OIL COMPARTMENT OIL COMPARTMENT BASE WIT...

Страница 69: ...9 Drawings Maschinenfabrik Reinhausen GmbH 2020 69 5993419 02 EN VACUTAP VMS 9 2 Selector ...

Страница 70: ...S NOTED SHEET MATERIAL NUMBER SERIAL NUMBER THROUGH HOLE VERTICAL 36 16 10 11 O 8 20 THROUGH HOLE HORIZONTAL A A B B M III 350 500 600Y VM III 350 500 650Y VMS III 400 650Y C M II 352 502 602 VM II 352 502 652 M I 351 501 601 VM I 351 501 651 M III 350 500 600Y VM III 350 500 650Y VMS III 400 650Y C M II 352 502 602 VM II 352 502 652 M I 351 501 601 VM I 351 501 651 M III 350 500 600Y VM III 350 5...

Страница 71: ...9 Drawings Maschinenfabrik Reinhausen GmbH 2020 71 5993419 02 EN VACUTAP VMS 9 3 On load tap changer head ...

Страница 72: ...COMMUNICATION OF ITS CONTENTS TO OTHERS WITHOUT EXPRESS AUTHORIZATION IS PROHIBITED OFFENDERS WILL BE HELD LIABLE FOR THE PAYMENT OF DAMAGES ALL RIGHTS RESERVED IN THE EVENT OF THE GRANT OF A PATENT UTILITY MODEL OR DESIGN A2 O Ring 44 2 5 7 TRANSFORMER COVER Z CENTERING BOLT DRIVE SIDE OF SELECTOR SCREENING RING WITH Um 170 245 300kV ONLY M SUPPORTING FLANGE LIFTING TRAVERSE LIFTING TRAVERSE O RI...

Страница 73: ...HE GRANT OF A PATENT UTILITY MODEL OR DESIGN A1 M DRIVE SIDE OF SELECTOR E1 BLEEDING FACILITY FOR ON LOAD TAP CHANGER HEAD E2 BLEEDING FACILITY FOR SPACE UNDER THE HEAD OUTSIDE THE TAP CHANGER OIL COMPARTMENT SAME PIPE CONNECTION AS R S Q OR BLEEDER SCREW CAN BE USED Q CONNECTION FOR OIL RETURN PIPE OR TAP CHANGE SUPERVISORY CONTROL S CONNECTION FOR SUCTION PIPE R CONNECTION FOR PROTECTIVE RELAY E...

Страница 74: ......

Страница 75: ......

Страница 76: ...9 Drawings Maschinenfabrik Reinhausen GmbH 2020 76 5993419 02 EN VACUTAP VMS 9 4 Tools 9 5 Additional drawings ...

Страница 77: ...SIC CONNECTION DIAGRAM 22 22 0 ON LOAD TAP CHANGER HEAD M III 350 Y M I 1503 AND VM III 350 Y VM I 1503 VARIANTS OF THE ON LOAD TAP CHANGER HEAD INSTALLATION DRAWINGS M III 350 Y M I 1503 VM III 350 Y VM I 1503 INSTALLATION POSITION OF THE SELECTOR CONNECTION CONTACTS HORIZONTAL DRIVE SHAFT PARALLEL BRIDGES CONNECTING LEAD 3W 1G 3G SWIVEL RANGE OF THE GEAR UNIT SCREENINGS AT TAP SELECTOR AND CHANG...

Страница 78: ...COMMUNICATION OF ITS CONTENTS TO OTHERS WITHOUT EXPRESS AUTHORIZATION IS PROHIBITED OFFENDERS WILL BE HELD LIABLE FOR THE PAYMENT OF DAMAGES ALL RIGHTS RESERVED IN THE EVENT OF THE GRANT OF A PATENT UTILITY MODEL OR DESIGN A4 CONTACT ARRANGEMENT ON SELECTOR BASIC CONNECTION DIAGRAMS ARRANGEMENT OF CONTACTS AT THE SELECTOR ON LOAD TAP CHANGER HEAD VARIANTS OF THE ON LOAD TAP CHANGER HEAD INSTALLATI...

Страница 79: ......

Страница 80: ...nfabrik Reinhausen GmbH Falkensteinstrasse 8 93059 Regensburg 49 0 941 4090 0 sales reinhausen com www reinhausen com 5993419 02 EN VACUTAP VMS 02 20 Maschinenfabrik Reinhausen GmbH 2020 THE POWER BEHIND POWER ...

Отзывы: