25
Commissioning
All factory fitted valves etc. are fitted using a thread sealant. If this
seal is broken it should be re-sealed using a suitable sealant. It is
the installer’s responsibility to ensure all the connections are water
tight prior to leaving the property.
1. Ensure the drain on the cold feed pipework is closed.
2. Open a hot tap the furthest distance from the unit.
3. Gradually open the cold mains isolator valve and fill cylinder
until water appears at the hot tap. Attend to each hot water
outlet in turn and ensure water flow is obtained at each outlet
expelling any air within the pipework.
4. To ensure the safety valves are operating correctly, turn the
tops of the valves independently to ensure water passes
through the valve and into the tundish. Once this is confirmed,
open both valves together allowing as much water as possi-
ble to flow through the tundish. At this point make sure that
your discharge pipework is free from debris and is transport-
ing the water away to waste effectively. The valves can then
be released and a check should be made to ensure they have
re-seated correctly.
5. Switch on the Mixergy cylinder and check for correct operation.
Mixergy cylinder come supplied in ‘eco mode’ which is de-
signed to satisfy the minimum charge requirements of BS EN
50440:2015 M draw profile. Pressing any button on the gauge
will exit eco mode. To re-enable eco mode, hold down power
and illuminate buttons simultaneously for 10 seconds.
6. Connect the cylinder to the internet by pairing to the included
powerline adapter. For more information on pairing the cylin-
der to the adapter, please reference page 26.
Ensure the cylinder’s gauge illuminates and all but-
tons (boost -, boost + and power) work correctly. For
further information on gauge operation please refer-
ence the user guide.
Содержание M0008
Страница 15: ...15 Installation electrical...
Страница 16: ...16 Installation electrical...
Страница 33: ...33 Service record Service date Serviced by Comments...
Страница 35: ......