105
9. Removing linear expansion valve
(1) Remove the service panel. (See photo 1.)
(2) Remove the top panel. (See photo 1.)
(3) Remove the front panel. (See photo 1.)
(4) Remove the conduit cover and cord cover.
(5) Remove the back panel. (See photo 1.)
(6) Remove the electrical parts box. (See photo 5.)
(7) Remove the linear expansion valve coil . (See photo 10.)
(8) Collect the refrigerant.
(9) Remove the welded part of linear expansion valve.
Note 1: Collect refrigerant without spreading it in the air.
Note 2: The welded part can be removed easily by remov-
ing the back panel.
Note 3: When installing the linear expansion valve, cover
it with a wet cloth to prevent it from heating (250˚F
or more), then braze the pipes so that the inside
of pipes are not oxidized.
OPERATING PROCEDURE
PHOTOS
8. Removing the four-way valve
(1) Remove the service panel. (See photo 1.)
(2) Remove the top panel. (See photo 1.)
(3) Remove the front panel. (See photo 1.)
(4) Remove the conduit cover and cord cover.
(5) Remove the back panel. (See photo 1.)
(6) Remove the electrical parts box. (See photo 5.)
(7) Remove the solenoid valve coil <Four-way valve> (See photo 8.)
(8) Collect the refrigerant.
(9) Remove the welded part of four-way valve.
Note 1: Collect refrigerant without spreading it in the air.
Note 2: The welded part can be removed easily by remov-
ing the right side panel.
Note 3: When installing the four-way valve, cover it with a
wet cloth to prevent it from heating (250˚F or more),
then braze the pipes so that the inside of pipes
are not oxidized.
Photo 10
Photo 11
10. Removing the high pressure switch (63H)
(1) Remove the service panel. (See photo 1.)
(2) Remove the top panel. (See photo 1.)
(3) Remove the front panel. (See photo 1.)
(4) Remove the conduit cover and cord cover.
(5) Remove the back panel. (See photo 1.)
(6) Remove the electrical parts box. (See photo 5.)
(7) Pull out the lead wire of high pressure switch.
(8) Collect the refrigerant.
(9) Remove the welded part of high pressure switch.
Note 1: Collect refrigerant without spreading it in the air.
Note 2: The welded part can be removed easily by
removing the back panel.
Note 3: When installing the high pressure switch, cover it
with a wet cloth to prevent it from heating (210˚F
or more), then braze the pipes so that the inside
of pipes are not oxidized.
Reactor fixing screw
High pressure
switch (63H)
Reactor fixing screws
Reactor
(ACL)
Electrical
parts box
11. Removing the reactor (ACL)
(1) Remove the service panel. (See photo 1.)
(2) Remove the top panel. (See photo 1.)
(3) Remove the front panel. (See photo 1.)
(4) Remove the back panel. (See photo 1.)
(5) Remove 3 reactor fixing screws (4
✕
20) and remove the
reactor.
w
The reactor is attached to the rear of the electrical parts box.
Photo 12
Charge plug
Four way valve
Linear expansion
valve coil (LEV-A)
Linear expansion valve
Four way valve
fixing screw
Four way valve coil
(21S4)
OC367C--4.qxp 07.6.20 0:58 PM Page 105
Содержание PUY-A12NHA
Страница 120: ...120 FUNCTIONAL PARTS PUZ A18NHA PUY A12NHA PUY A18NHA 1 2 3 4 5 6 7 8 9 10 11 12 23 13 16 17 15 18 19 20 22 21 14 ...
Страница 124: ...124 FUNCTIONAL PARTS PUZ A42NHA PUY A42NHA 12 3 5 6 10 2 9 1 7 8 11 13 14 15 16 17 19 20 21 22 23 24 25 26 27 28 4 1 18 ...
Страница 135: ...135 ...