OM-252 624 Page 68
10-3. Run-In Procedure Using Resistance Grid
S-0684
!
Stop engine.
!
Do not touch hot exhaust
pipe, engine parts, or load
bank/grid.
!
Keep exhaust and pipe away
from flammables.
NOTICE
−
Do not perform run-in
procedure at less than 20 volts weld
output and do not exceed duty
cycle or equipment damage may
occur.
1
Resistance Grid
Use grid sized for generator rated
output.
Turn Off grid.
2
Welding Generator
Place Welder Selector switch in the
A position (Single Operator) and
rotate A/V control to minimum.
Place Process Selector switch in
Stick position.
3
Weld Cables
Connect grid to generator Side A
weld output terminals using proper
size weld cables with correct con-
nectors (polarity is not important).
4
Voltmeter
5
Clamp-On Ammeter
Connect voltmeter and ammeter as
shown, if not provided on generator.
Start engine and run for several
minutes.
Set grid switches and then ad-
just generator A/V control so
load equals rated voltage and
current of the generator (see
nameplate, rating label, or the
specifications section in this
manual).
Check generator and meters after
first five minutes then every fifteen
minutes to be sure generator is
loaded properly.
NOTICE
−
Check oil level frequent-
ly during run-in; add oil if needed.
It is recommended to run the weld-
ing generator for two hours mini-
mum and up to four hours under
load. Place A/V control in minimum
position, then shut down grid to
remove load. Run engine several
minutes at no load.
!
Stop engine and let cool.
6
Engine Exhaust Pipe
Repeat procedure if wetstacking is
present.
1
3
5
+
4
2
6
Содержание big blue 700 duo pro
Страница 51: ...OM 252 624 Page 47 6 8 Fuel Hour Gauge Descriptions...
Страница 66: ...OM 252 624 Page 62 SECTION 9 ELECTRICAL DIAGRAMS Figure 9 1 Circuit Diagram For Export Welding Generator...
Страница 67: ...OM 252 624 Page 63 250 340 E...
Страница 68: ...OM 252 624 Page 64 Figure 9 2 Circuit Diagram For North American Welding Generator...
Страница 69: ...OM 252 624 Page 65 249 603 D...