6.3.6 Re-installation while the outdoor unit need to be repaired
1. Evacuation for
the whole system
Procedure:
1).
Confirm that both the 2-way and 3-way valves are set to the opened position.
2). Connect the vacuum pump to 3-way valve’s service port.
3). Evacuation for approximately one hour. Confirm that the compound meter indicates
-0.1Mpa.
4). Close the valve (Low side) on the charge set, turn off the vacuum pump, and confirm that
the gauge needle does not move (approximately 5 minutes after turning off the vacuum pump).
5). Disconnect the charge hose from the vacuum pump.
Содержание MFM-24ARN1-Q
Страница 12: ...Floor Standing MFM DM16 01 01 25en Service manual 12 5 2 MFM 48ARN1 R Indoor unit Outdoor unit MOU 48HN1 RB6W...
Страница 13: ...DM16 01 01 25en Floor Standing MFM 13 Service manual 5 3 MFM 60ARN1 R Indoor unit Outdoor unit MOUL 60HN1 R...
Страница 34: ...Floor Standing MFM DM16 01 01 25en Service manual 34 7 2 Control Panel Control Buttons and Functions...
Страница 50: ...Floor Standing MFM DM16 01 01 25en Service manual 50 10 2 9 Overload of current 1...
Страница 52: ...Floor Standing MFM DM16 01 01 25en Service manual 52 10 2 11 Refrigerant Leakage Detection...
Страница 53: ...DM16 01 01 25en Floor Standing MFM 53 Service manual 10 2 12 Temperature protection of compressor discharge...