9
OPERATION MANUAL
3 INSTALLATION
Position the press assembly in a suitable location. The dimensions can be found in the specifications
list on page 4. The base of the press should sit on a concrete floor at least 150mm thick.
NOTE !
The press must be permanently mounted to the floor with bolts through the four legs.
Fig. 5
The press should be level and stable. Place a level across the and
along the table and adjust until the table is level.
The table legs are fitted with and adjusting screw and a hole for
the hold down bolt
WARNING
The machine is top heavy when the bolster
is in the top position
3.3 HYDRAULIC OIL TANK
Once the press has been installed and bolted to the floor the
hydraulic oil level needs to checked in the 40 ltr tank before
operating. The oil level should be half way up the site glass
on the side of the tank (Fig. 6) Check all hydraulic hoses
to be sure the fittings and couplers are tight and leak free.
Check the hose positions to be sure the hoses are located in
an area where they will avoid damage during press opera-
tions.
3.2 ELECTRICAL CONNECTION
The press needs to be connected to the power supplied. The power requirements are listed below
VOLTAGE.........................................415 Volts 3 Phase 50 Hz
AMPS.................................................15
Amps
The press is supplied without any lead and requires a qualified electrician to connect the machine
to the power supply. If a plug and lead is to be fitted then either a service engineer of qualified elec-
trician ahould be used.
WARNING
This machine has an electrical hazard.
Electrical cabinets must not be opened except by a
qualified electrician.
Fig. 6
3.1 PLACEMENT & LEVELING