Pre-Start Inspection Checklist
The operator must conduct a Pre-Start Inspection of the machine before each work shift.
DO NOT use a damaged or malfunctioning machine.
Initial
Description
Be sure that the operator’s manual are complete, legible and in the storage container located in the
platform.
Be sure that all decals are legible and in place. See Decals section.
Check for hydraulic oil leaks.
Check for battery fluid leaks.
Check the following components or areas for damage, improperly installed or missing parts and
unauthorized modifications:
Electrical components, wiring and electrical cables
Battery connections
Hydraulic hoses, fittings, cylinders and manifolds
Battery pack and connections
Drive motors
Slide blocks/wear pads
Tires and wheels
Ground strap
Limit switches, alarm and beacon
Nuts, bolts and other fasteners
Platform entry gate
Beacons and alarms
Maintenance Lock
Platform extension
Scissor pins and retaining fasteners
Platform control handle
Brake release components
Pothole guards
Check entire machine for:
Cracks in welds or structural components.
Dents or damage to machine.
Be sure that all structural and other critical components are present and all associated fasteners and
pins are in place and properly tightened
Be sure that guard rails are properly installed and secured, and that all pins and bolts are properly
fastened.
Be sure that the chassis trays are closed and latched and the batteries are properly connected.
NEVER perform work or inspection on the machine with the platform
elevated without first blocking the scissor assembly with the
Maintenance Lock����� See page 21 for instructions�����