Page 36
Diagram 3
Horizontal Flueing with Two (2) 90
o
Elbows
Option
V
H + H1
A)
1' (305mm) Minimum
2' (610mm) Maximum
B)
2' (610mm) Minimum
5' (1.5m) Maximum
C)
3' (914mm) Minimum
8' (2.4m) Maximum
D)
4' (1.22m) Minimum
11' (3.35m) Maximum
E)
5' (1.5m) Minimum
14' (4.27m) Maximum
F)
6' (1.86m) Minimum
15' (4.5m) Maximum
Horizontal Flueing with Two (2) 90
o
Elbows
Option
V
H
H + H1
A)
1' (305mm) Min. 1' (305mm) Max. 3' (914mm) Max.
B)
2' (610mm) Min. 3' (0.91m) Max.
6' (1.86m) Max.
C)
3' (914mm) Min. 5' (1.5m) Max.
9' (2.7m) Max.
D)
5' (1.5m) Min.
8' (2.4m) Max.
12' (3.6m) Max.
Horizontal Flueing with Three (3) 90
o
Elbows
Horizontal Flueing with Three (3) 90
o
Elbows
Diagram 5
Diagram 4
Diagram 6
With the above options, maximum total pipe length
if 37 feet with minimum of 6 feet total vertical and
maximum 15 feet total horizontal.
Please note minimum 300mm between 90
o
elbows is required.
Option
V
H
H + H1 + H2
A)
2' (610mm) Min. 1' (305mm) Max. 3' (914mm Max.
B)
3' (914mm) Min. 3' (914mm) Max. 6' (1.86m) Max.
C)
4' (1.22mm) Min. 5' (1.5m) Max.
9' (2.7m) Max.
D)
5' (1.5m) Min.
7' (2.13m) Max.
12' (3.6m) Max.
With the above options, maximum total pipe length
if 37 feet with minimum of 5 feet total vertical and
maximum 12 feet total horizontal.
Please note minimum 305mm between 90
o
elbows is required.
With the above options, maximum total pipe length if
37 feet with minimum of 5 feet total vertical and
maximum 12 feet total horizontal.
Please note minimum 305mm between 90
o
elbows is required.
Option
V + V1
H + H1
A)
2' (610mm) Minimum
3' (914mm) Maximum
B)
3' (914mm) Minimum
6' (1.86m) Maximum
C)
4' (1.22m) Minimum
9' (2.7m) Maximum
D)
5' (1.5m) Minimum
12' (3.6m) Maximum
With the above options, maximum total pipe length if
37 feet with minimum of 5 feet total vertical and
maximum 12 feet total horizontal.
Please note minimum 305mm between 90
o
elbows is required.