SINTER-1
PRE-INSTALLATION GUIDE : METAL X SYSTEM
Due to its exhaust, power, and gas supply requirements, the Sinter-1 requires the
most complex facilities planning and installation of the Metal X system. However,
the pre-installation steps for the device itself are straightforward.
Before you uncrate and transport your Sinter-1 furnace, you must fully comply with
the site requirements and procedures in the
Metal X System Facilities Guide
.
SPACE AND MATERIALS
IMPORTANT NOTE:
The Sinter-1 shipping crate contains a large number of boxes;
all but one are simply set aside for the Installer. You are responsible for moving the
Sinter-1 furnace to its operating location and installing the gas supply panel, but
every other item in the shipping crate is for the Installer.
Take special note of the 60lb Kanthal furnace tube, which is secured in a foam
cradle beneath the furnace. The entire pallet, with the tube inside, must be laid flat
in a secure location to await final installation. Be sure to allocate space to store the
pallet and tube when planning the pre-install procedure. Use safe lifting techniques
when moving the pallet.
Along with space to store the tube/pallet and the remaining boxes, you must prepare
a 10’x10’ uncrating area with a clear path to the operating location. You will need a
power drill (Phillips #2 bit) and 9/16” socket wrench to uncrate the device.
A forklift is recommended for moving the Sinter-1 from crate to operating site, using
lifting straps to secure the unit; alternatively, it can be carefully transported by 2-3
people using safe lifting techniques. It weighs approximately 200lbs. Do not attempt
to carry the Sinter-1 singlehanded.
Always wear work gloves when lifting the Sinter-1; the bottom of the device has
rough edges.
When the requirements in the
Facilities Guide
are met and uncrating and storage
areas are available, you are ready to uncrate your Sinter-1.