1 OPERATION
TO MAKE A BALE : HD & LP Units
1.
Feed material into baler.
If starting a new bale, place a large flat piece of mater-
ial flat on the baler floor. NOTE: Do not attempt to overfill the feed chamber by
forcing material into the chamber with the feed gate. This can cause gate release
malfunction and may damage baler.
2.
Pull gate handle down to close feed gate
. NOTE: Check red warning light
before closing feed gate. If gate is open and light is on, discontinue use of the
baler and call for service.
3.
To start the baler, insert the key into the keyswitch and turn to the ON
position.
4.
Press the AUTOCYCLE button.
The platen will make a complete cycle down
and back up. When the platen is in the full up position, the feed gate will auto-
matically open and the motor will automatically shutdown.
5.
Repeat steps 1 through 4 until platen stops in down position and “BALE MADE”
light comes on.
NOTE: In normal operation, the feed gate will be open when you walk up to
place material into the baler. For added security, the feed gate can be manually
closed after the AUTOCYCLE(S). To open the gate, you will have to insert the
key into the keyswitch and run the baler through a complete AUTOCYCLE.
IN CASE OF EMERGENCY:
Push the large red button to
STOP
OPERATING INSTRUCTIONS - MAKING A BALE
WARNING:
DO NOT OPERATE BALER UNTIL OPERATING INSTRUCTIONS ARE
UNDERSTOOD.
See pages 1-3 through 1-5 for control panel layout and location.
1-7
WARNING:
Interlocks and safety devices were installed on this unit for
your protection.
Never disable or bypass any interlock or safety
device
. Failure to comply with this warning could result in serious injury or
death.
Содержание V-4830
Страница 38: ...2 MAINTENANCE PANEL BOX FOR HD AND LP BALERS 2 14...
Страница 39: ...2 MAINTENANCE PANEL BOX FOR V 6030 V 4830 TRANSFORMER PRINTED CIRCUIT BOARD IEC MOTOR STARTER 2 15...
Страница 43: ...2 MAINTENANCE HYDRAULIC SCHEMATIC FOR VERTICAL BALERS TYPICAL 2 19...
Страница 44: ...2 MAINTENANCE HYDRAULIC SCHEMATIC FOR V 6042LP 2 20...