15
combustible
E, F - easily
combustible
Asphalt board, fibreboards, cellulose materials, polyurethane,
polystyrene, polyethylene, PVC, ....
A boiler placement:
• basic environment AA5 / AB5 according to STN 33 2000-3
• Before the boiler must be working space of min. 1000 mm
• The minimum distance between the rear of the boiler and the wall is 400 mm
• on the tray fuel gap min. 500 mm in case of collection of feed screw
• The minimum distance from the left side wall 100 mm
• the boiler at least 450 mm for the possibility exchanger cleaning and refueling
Location of the boiler to the electrical network:
• boiler must be positioned so that the plug in socket (230V / 50Hz) accessible at all
times.
• boiler is connected to power. Fixed network attached corded completed a standardized
plug
• Protection against electric shock must be ensured in accordance with the applicable
EN STN (see Sec. 1.4)
Location of fuel:
• for proper combustion in the boiler is necessary to use dry fuel. We recommend to
store the pellets in their original packaging from the manufacturer (PET bags) on a dry
place.
• It is forbidden to store the fuel for the boiler, stored next to the boiler at a distance less
than 400 mm
• The manufacturer recommends to observe distance between the boiler and fuel min.
1000 mm or put fuel into a different room than the installed boiler.
To the room where the boiler is installed, it must be ensured steady supply and exhaust
air for combustion and ventilation. Pipe connection of the heating system or water
heater ducts have to be provided by a specialist with the licence.
When connecting the boiler to the heating system it must be at the lowest point
and as close to the boiler a drain valve.