1. Set the ac supply and rectifier controls as shown in Table
5-C.
2. Move the strap P14 and the straps provided for options
“Q” and “T” on the CM1 option board from normal
position to initial charge position as shown in Figure 6-2.
3. At the ac service panel supplying power to the rectifier,
insert the input fuses assigned to the rectifier or turn the
circuit breaker On.
4. Close the rectifier door and turn the POWER switch On.
The green Power LED must light. (If not, do not attempt to
turn On the circuit breaker. Troubleshoot the problem per
Section 7.) Wait 10 seconds.
Table 5-C: Rectifier Control Settings for Initial Battery
Charge
Controls
Position/Status
Rectifier POWER switch
Off (down)
Rectifier DC OUTPUT circuit breaker
Off (down)
OUTPUT VOLTS ADJ potentiomneter
Fully
counterclockwi
se
Plant control connector J2A on CM2
control board mounted on inside of door
Disconnected
from P2A on
CM2
Warning
Do not remove the ZJ option strap on the CM1 option board
when the rectifier is equipped with a 205A1 control board.
Note
If the rectifier continues to operate, proceed to Step 5. If the
rectifier shuts down due to initial high voltage, monitor the
RECT V voltage. When this reading reaches 26 volts for
24-volt plants, or 52 volts for 48-volt plants, turn On the
circuit breaker. If the rectifier shuts down for any other
reason, such as component failure, see Section 7,
Troubleshooting and Adjustments.