Step A: See “Ordering Information” in Section 2 for details on
obtaining additional circuit breakers.
Step B: Alarms may be issued during the installation process
(e.g. by a new circuit breaker in the OFF position). Notify the
alarm reporting center that alarms may be received.
Step C: Open the dc distribution cover panel, taking care not to
disturb any load-carrying circuit breakers.
Step D: Locate the intended new breaker position. Spare circuit
breakers may or may not already be in place on the dc
distribution panel, as ordered. Alternatively, spare distribution
leads may or may not have been run to the new load location.
If a spare circuit breaker is already plugged in the next available
position, verify that the breaker is OFF.
If a new breaker must be added, switch it to the OFF position.
Plug in the new breaker. If possible, visually verify that line,
load and alarm connectors are properly mated. (See Figure 2-4).
Step E: If leads have not already been run to the intended load
from a spare circuit breaker position (e.g., during the initial plant
installation), install these leads by following Step G in paragraph
“Sequence of Tasks” above.
Step F: Mark the new circuit on the distribution cover panel
label.
DANGER
Battery voltage is present behind the distribution cover panel.
Remove all jewelry before working in this area. Use insulated
tools only.
Caution
Accidentally or intentionally turning a circuit breaker off may
affect service to load equipment. Take care not to disturb
load- carrying circuits.
DANGER
Do not plug a closed circuit breaker into a circuit which may
be connected. Arcing may result in personnel injury and
equipment damage.