Operating instructions T80PL 2010 12/21 (01/2010)
4.5
Fetching and sending the platform lift
(standard version)
Ensure before each trip that the acoustic and, if present, the visual (optional)
warning signals work. The T80 platform lift can be fetched from or sent to another
station from any station. To do this, the key switch must be inserted at the
respective station, turned in the appropriate direction and held in this position.
The platform lift does not react immediately, but after a delay time of approx. 2
seconds.
Note:
The platform lift drives from the external control point only in
the folded up condition, i.e. the base of the platform must be folded
up and the safety barriers lowered to the bottom.
Attention:
In the case of a storey circuit (more than two stations) the platform lift
is to be fetched or sent as follows: If the T80 platform lift has arrived
at one of the middle stations, it stops there and opens or can be
opened respectively. If the platform lift in not supposed to stop (open)
there, the drive control on the external control unit must be briefly
released and then pressed again immediately so that the platform
continues to drive.
Note:
an LED is mounted on the radio transmitter for fetching/sending the
platform lift.
GREEN: batteries are OK
ORANGE: the battery power is diminishing; renew the batteries at your earliest
convenience
RED: the battery power is very low; replace the batteries immediately
Fetching and sending the platform lift
(special version 1) [via the external
control unit, only with 3-position key switch (p.7, 8/item 2) for a trip with the
platform open via the external control unit]. This option must be activated by a
specialist inside the controller. It must be ensured that no third person can
suddenly get/jump into the path of the lift.
Condition: driving area is 100% in
view !!!!
The key switch (p.7, 8/item 2) is to be set to position -II-, otherwise as in 4.5.
Fetching and sending the platform lift
(special version 2) [via the internal
controller, only with 3-position key switch (p.7, 8/item 2)]. This option must be
activated by a specialist inside the controller.
The platform can be driven via the internal controller in the folded up condition.
The key switch (p.7, 8/item 2) is to be set to position -II- in order to do this. The
platform lift can now be driven via the internal controller (p.7, 8/item 1).
If there are more than two stations: The platform lift will stop automatically at
each intermediate station and will open if an automatic platform is fitted. If this is
not desired, a new drive command must be given and the platform lift continues to
drive.