Commissioning Menu Screen 8:
Shuttle Full Sweep
Pressing
▼
7
times
displays
Commissioning
Full
sweep:
N
or
Y
This
feature
allows
the
user
to
manually
‘sweep’
the
shuttle
inside
the
main
valve
body
from
full
hot
to
full
cold
position
in
order
to
verify
mechanical
integrity
of
the
device,
and
verify
that
the
valve
is
traveling
the
entire
range
of
its
expected
travel
or
operating
range.
To
initiate
a
full
sweep,
press
ENTER
and
change
the
flashing
value
to
‘
Y
’
(yes)
and
press
ENTER
to
confirm.
Commissioning
Menu
Screen
9:
Minimum
Alarm
Temperature
for
Temperature
Sensor
#5
Note:
There
are
four
(4)
additional
RTD
temperature
probe
provisions
(T5,
T6,
T7,
T8)
if
the
Nucleus
is
equipped
with
an
optional
Daughter
Board.
Please
see
Screen
6
(Page
7)
from
Options/Equipped
section
above
and
if
Daughter
Board
is
showing
‘
Y
’
(Yes),
then
these
temperature
probes
should
be
configured,
if
they
are
being
utilized.
Pressing
▼
8 times
displays
Commissioning
Temp
5
min:
32F
This
is
the
minimum
temperature
for
RTD
probe
T5.
Any
temperature
below
this
setting
at
T5
will
trigger
an
error
message.
Default
setting
is
32
˚
F.
16