Filling with liquid paraffin
Software control
If the instrument has been filled
with liquid paraffin, the instrument's
internal calculation of the melting
time can be disabled.
To do so, in supervisor mode, open the
SERVICE
FUNCTIONS
(
Fig. 59
) window. Press
PARAFFIN
MELTING
.
Fig. 60
→
→
→
• If filling with already melted paraffin, the liquid
level must not exceed the
MAX
level mark (see
Fig. 58
) in the paraffin reservoir.
• After a paraffin reservoir is filled with paraf-
fin, it must be marked as full in the
REAGENT
STATUS
table.
A safety prompt ap-
pears that you have to
confirm with
YES
.
In the time window,
enter the desired de-
lay time and confirm
with
OK
.
Fig. 59
→
↓
5. Operation
Change the delay time only if you are absolutely sure that the entered time is correct.
If the instrument attempts to run a paraffin step with paraffin that is not completely melted,
substantial faults and malfunctions may result.
The temperature of filled liquid paraffin must not be greater than 70 °C to prevent damage to the
thermal fuse. Caution! Burn hazard.