Installation
549263_D_PUB_DATE_7_JUL_2014.DOC
INSTALLATION, MAINTENANCE AND USER' MANUAL
37
Installation on floor or steel base – rigid-mount machines
The drum of rigid-mount machines is fixed to the frame.
The floor and steel base (if used) underneath the machine
MUST
be stable enough to be able to absorb the dynamic loads
which are created during the spinning sequence, see the values
for each machine specified in table 1, 2.
Therefore, M16 anchor bolts - pos.4 – see figure 14 and 15 and
washers ø60 / ø16.5 x 6mm - pos.2 and M16 self locking nuts - pos.1
must be used so that the machine, the steel base (if used)
and floor form one integral unit – see figures 14 and 15.
The anchor bolts are not supplied with the machine. The washers
and nuts are supplied with the machine. The torque is 100Nm.
The existing concrete floor must be at least 120mm / 4.72" thick.
Dimensions for anchoring – see figures 10, 11 and table 22.
Check that the machine is installed in a level and stable manner
in all its corners. If necessary, level it up by means of stainless
or galvanised spacing washers, see figures 14, 15, 16, 17, pos.3
(washers are not supplied with the machine) inserted in between
the machine frame and the floor – see figures 16, 17. The dimensions
of the spacers must be the same as the dimension of the machine
frame in the place where the anchor bolts are located – 80x80mm.
Fit a washer and self locking nut on the anchor bolt and tighten
it with a torque wrench to a torque of
100Nm
.
It is advisable to recheck the torque after a short period
of the machine operation.
The bottom frame of the machine shall be used for the purpose
of lifting the whole machine.
Place the machine over the four drilled holes.
Check that the machine is seated in a perfectly level manner.
The anchoring of the machine or the steel base can be carried
out by means of mechanical or chemical anchor bolts which
must be able to form one integral unit with the floor (they are
not supplied with the machine).
WASHER
CONCRETE
FLOOR
Figure 14 – Rigid-mount machines,
Installation on floor
Figure 15 – Rigid-mount machines,
Installation on a steel base and floor
WASHER
CONCRETE
FLOOR
BOLT M16
(SUPPLIED
WITH THE STEEL
BASE)
Figure 17 – Rigid-mount machines,
8-11-14 kg / 18-25-30 lb,
18-24-28 kg / 40-55-65 lb – normal spin
WASHER
CONCRETE
FLOOR
3
AS NEEDED
Figure 16 – Rigid-mount machines,
18-24-28 kg / 40-55-65 lb – medium spin
LEVELING
THE MACHINE UP
LEVELING
THE MACHINE UP
WASHER
3
AS NEEDED
CONCRETE
FLOOR