3 WORK
24
E00888-01
Main work
–
Check throttle cable routing.
Both throttle cables must be routed, side by side, on the
back of the handlebars, above the fuel tank bracket on the
right of the frame to the throttle valve body. Both throttle
cables must be secured behind the fuel tank contact area
rubber band.
» If the throttle cable routing is not as specified:
–
Correct throttle cable routing.
Finishing work
–
Install the fuel tank. (
–
Mount the seat. (
3.8
Installing the shock absorber
E00870-10
Main work
–
Push splash protector
1
to the side and position the shock
absorber. Mount and tighten screw
2
.
Guideline
Screw, top
shock absorber
M12
80 Nm (59 lbf ft)
Loctite
®
2701™
–
Mount and tighten screw
3
.
Guideline
Screw, bottom
shock absorber
M12
80 Nm (59 lbf ft)
Loctite
®
2701™
Info
The heim joint for the shock absorber at the swingarm
is Teflon-coated. It must not be greased with grease or
with other lubricants. Lubricants dissolve the Teflon
coating, thereby drastically reducing the service life.
Finishing work
–
Remove the motorcycle from the lift stand. (