7
FRAMING
Follow vent pipe manufacturer’s installation instructions for horizontal terminations.
Include required 1-
1/2” (38mm) top clearance (at wall pass
-
thru) and 1” (25mm) sides
and bottom clearances for approved rigid vent systems.
HORIZONTAL TERMINATIONS
Follow vent pipe manufacturer’s installation instructions for vertical terminations.
A minimum 1” (25mm) clearance on all sides of vertical vent pipe must be maintained.
VERTICAL TERMINATIONS
A. Locate metal bar (glass latching mechanism) below glass frame.
B. To release glass assembly, pull latch mechanism knobs out, then immediately
down, securing metal bar onto stops.
C. Pull bottom of glass assembly out, lifting up and off tabs at top of firebox.
GLASS FRAME ASSEMBLY
REMOVE GLASS FRAME ASSEMBLY
INSTALL GLASS FRAME ASSEMBLY
Pull knobs out and
down to release.
IMPORTANT
Vent cap location must be in compliance with guidelines on page 11
of this manual
.
Minimum venting: 75” (1.905m) from floor or hearth to top of vent pipe.
Wall pass-thru required for all horizontal runs. Refer to vent manufacturer’s to determine which pass-thru will work best for
your application.
Figure 7b
WARNING
DO NOT OPERATE THIS FIREPLACE WITH THE GLASS REMOVED, CRACKED OR BROKEN. REPLACEMENT OF GLASS
ASSEMBLY, #700-015T SHOULD BE DONE BY A LICENSED OR QUALIFIED SERVICE PERSON.
A. Place glass frame assembly top over tabs at top of firebox.
B. Pull bottom handles out and up to secure glass frame assembly bottom.
Refer to vent pipe manufacturer’s
instructions for specific height (H)
and width (W) framing dimensions.
75” (1.905m) min.
to top of vent pipe
Figure 7a