Mount the steel conduits from the casings and up towards the sonar room where the
transmitter and receiver units are located.
The steel conduits are laid as required by the vessel structure and the location of the
blister and sonar room. The conduits may be bent if required, but not more than 30
degrees. If a bend beyond 30 degrees is required a higher conduit diameter may be
required. Please consult Kongsberg Maritime if this is the case.
The upper opening of the steel conduits should be minimum 2 metres above the
vessel’s waterline as specified by the classification society. If the openings of these
conduits are under the water level, then special acceptances are needed from the
classification society.
4
Mount an air outlet on top of each conduit.
Each conduit should have an air outlet on top. This can be performed by a small
ball valve and a 1 " pipe routed above the deck.
5
Close the top of the steel conduits with a cable sealing system.
Kongsberg Maritime recommends the use of sealing from Roxtec, Brattberg or
similar.
6
If relevant, allow the maritime authority and/or classification society to inspect and
approve the design and the installation of the steel conduit.
Installing the TX mounting frames
The mounting frame have been designed to offer a reliable and maintenance friendly
installation method for the SBP 29
Prerequisites
The casings should be manufactured with threaded holes for mounting of the frames. If
not, access from rear side will be required.
Note
Engineers from Kongsberg Maritime must be present to install the transducer mounting
frames.
• The casings have been installed and machined according to the requirements.
• All relevant vessel and SBP 29 drawings must be available.
• All relevant work instructions, procedures and standards must be available.
• All relevant personnel (skilled shipyard workers) and their tools must be available.
The following specific tools and items are required for this task:
• Torque wrench
• Loctite 242 (removable medium strength threadlocker)
SBP 29 Installation Manual
Содержание SBP 29
Страница 1: ...451253 A November 2019 Kongsberg Maritime AS SBP 29 Sub bottom profiler Installation Manual ...
Страница 57: ...451253 A 57 Cable plan overview Overview of the SBP 29 cable plan Cable layout and interconnections ...
Страница 111: ...451253 A 111 Figure 12 862 216859 Drawing files ...
Страница 112: ...112 451253 A Figure 13 307904 SBP 29 Installation Manual ...
Страница 113: ...451253 A 113 Figure 14 862 218001 Drawing files ...
Страница 114: ...114 451253 A Figure 15 871 219193 SBP 29 Installation Manual ...
Страница 115: ...451253 A 115 Figure 16 871 219201 Drawing files ...
Страница 116: ...116 451253 A Figure 17 388168 SBP 29 Installation Manual ...
Страница 117: ...451253 A 117 Figure 18 871 219187 Drawing files ...
Страница 118: ...118 451253 A Figure 19 821 219199 SBP 29 Installation Manual ...
Страница 119: ...451253 A 119 Figure 20 388235 Drawing files ...
Страница 120: ...120 451253 A Figure 21 871 219198 SBP 29 Installation Manual ...
Страница 121: ...451253 A 121 Figure 22 388148 Drawing files ...
Страница 122: ...122 451253 A Figure 23 315550 SBP 29 Installation Manual ...
Страница 123: ...451253 A 123 Figure 24 430751 Drawing files ...
Страница 124: ...124 451253 A Figure 25 871 212984 SBP 29 Installation Manual ...
Страница 125: ...451253 A 125 Figure 26 407070 Drawing files ...
Страница 126: ...126 451253 A Figure 27 448231_1A SBP 29 Installation Manual ...
Страница 127: ...451253 A 127 Figure 28 427512 Drawing files ...
Страница 128: ...128 451253 A Figure 29 435680 SBP 29 Installation Manual ...
Страница 129: ...451253 A 129 Figure 30 444783 Drawing files ...
Страница 151: ......
Страница 152: ... 2019 Kongsberg Maritime ...