Manufacturing and installing the casings
The transducer mounting frames needs to be mounted into a solid base construction
also called casing. The casings can be integrated in different kind of installation types
like a gondola, blister or flush in the hull.
Prerequisites
You must be equipped with a standard set of tools. This tool set must comprise the
normal tools for mechanical tasks. This includes different screwdriver types, pliers,
adjustable spanners, etc. Each tool must be provided in various sizes. We recommend
that all tools are demagnetized to protect your equipment. Depending on the tasks at
hand, additional tools may be required.
Observe the relevant rules and regulations related to welding. The quality of the welding
is critical to the safety of the vessel. Welding must only be done by a certified welder.
The final installation welds must be approved by the vessel’s national registry, the
corresponding maritime authority and/or classification society.
Before you can do this task, the following prerequisites must be met:
• All relevant vessel and SBP 29 drawings must be available.
• All relevant drawings have been approved by the classification society.
• All relevant work instructions, procedures and standards must be available.
• The installation principle has been determined.
• The physical location of the SBP 29 has been determined.
• The installation angles of the SBP 29 have been defined.
• All relevant personnel (naval architects, designers) and tools must be available.
Context
The casings must be individually designed for each vessel, and it is not a part of the
system delivery.
The casings must be provided (or manufactured) and installed by the installation
shipyard. It is the shipyard’s responsibility to get the installation approved by the
classification society.
The installation must be carried out according to arrangement drawings designed for the
specific vessel. Refer to the drawings included in the
Drawing File
, and the applicable
drawings prepared by the installation shipyard.
Note
Follow the general safety procedures. These units are heavy.
SBP 29 Installation Manual
Содержание SBP 29
Страница 1: ...451253 A November 2019 Kongsberg Maritime AS SBP 29 Sub bottom profiler Installation Manual ...
Страница 57: ...451253 A 57 Cable plan overview Overview of the SBP 29 cable plan Cable layout and interconnections ...
Страница 111: ...451253 A 111 Figure 12 862 216859 Drawing files ...
Страница 112: ...112 451253 A Figure 13 307904 SBP 29 Installation Manual ...
Страница 113: ...451253 A 113 Figure 14 862 218001 Drawing files ...
Страница 114: ...114 451253 A Figure 15 871 219193 SBP 29 Installation Manual ...
Страница 115: ...451253 A 115 Figure 16 871 219201 Drawing files ...
Страница 116: ...116 451253 A Figure 17 388168 SBP 29 Installation Manual ...
Страница 117: ...451253 A 117 Figure 18 871 219187 Drawing files ...
Страница 118: ...118 451253 A Figure 19 821 219199 SBP 29 Installation Manual ...
Страница 119: ...451253 A 119 Figure 20 388235 Drawing files ...
Страница 120: ...120 451253 A Figure 21 871 219198 SBP 29 Installation Manual ...
Страница 121: ...451253 A 121 Figure 22 388148 Drawing files ...
Страница 122: ...122 451253 A Figure 23 315550 SBP 29 Installation Manual ...
Страница 123: ...451253 A 123 Figure 24 430751 Drawing files ...
Страница 124: ...124 451253 A Figure 25 871 212984 SBP 29 Installation Manual ...
Страница 125: ...451253 A 125 Figure 26 407070 Drawing files ...
Страница 126: ...126 451253 A Figure 27 448231_1A SBP 29 Installation Manual ...
Страница 127: ...451253 A 127 Figure 28 427512 Drawing files ...
Страница 128: ...128 451253 A Figure 29 435680 SBP 29 Installation Manual ...
Страница 129: ...451253 A 129 Figure 30 444783 Drawing files ...
Страница 151: ......
Страница 152: ... 2019 Kongsberg Maritime ...