Verify that the processor is switched off.
3
.
Use AIR METER TL-2431 to measure negative static pressure in the EXHAUST
DUCT 30.5 cm (12 in.) from the end that is connected to the processor.
4
.
Adjust the gap between the BUILDING EXHAUST DUCT and the DUCT from the
PROCESSOR to obtain the required static pressure.
Negative Static Pressure, Water Head
DUCT DIAMETER
MIN
MAX
76 mm (3 in)
0.76 mm (0.03 in)
1.02 mm (0.04 in)
102 mm (4 in)
0.25 mm (0.01 in)
0.51 mm (0.02 in)
5
. Connect the EXHAUST HOSE to the EXHAUST CONNECTION of the PROCESSOR.
CAUTION:
Do not run the ML2000 P as long as the negative pressure of the EXHAUST is not correct !
Incorrect venting may cause serious damage.
FINAL CHECK-OUT:
1
.
Run the MINILOADER in continuous cycle, look and listen to all functions:
CASSETTE opening
FILM pick-up from CASSETTE
MAGAZINE opening
FILM pick-up from MAGAZINE
BLOW PIPE function
2
.
Mount all PANELS.
3
.
Clean all PANELS.
GAP
BUILDING EXHAUST DUCT
Duct from the PROCESSOR
figure 6-5
SM 3477
PREVENTIVE MAINTENANCE
KODAK AG, Stuttgart
6-5
6/1997
Содержание Miniloader 2000 P
Страница 6: ...TABLE OF CONTENTS SM 3477 6 1997 IV KODAK AG Stuttgart ...
Страница 10: ...TOOLS SM 3477 4 1997 1 2 KODAK AG Stuttgart ...
Страница 46: ...REPLACEMENTS SM 3477 6 97 2 36 KODAK AG Stuttgart ...
Страница 104: ...PARAMETER SM 3477 6 1997 4 10 KODAK AG Stuttgart ...
Страница 112: ......