6
FRAMING
Using 2x4s frame to local building codes.
DO NOT install against a Vapour Barrier or Exposed
Insulation.
Framing measurements have been adjusted to
accommodate a 1/2" thick finished wall. FIGURE 1
Combustible materials may be installed flush with top
of standoffs and sides of fireplace.
It is not necessary to install a hearth with this
fireplace system. Objects placed in front of the fireplace
should be kept a minimum of 24" away from the front face.
Gas line installation should be performed only after
Fireplace installation. Fireplace bottom supplies you with
two 6"x8" rectangular holes. The use of these holes
depends on valve and Fireplace location on riser or
upper floor.
SEE - THRU INSTALLATION INSTRUCTIONS
FRAMING DETAIL
HORIZONTAL RUN
WITH MIN. VERTICAL RUN
THROUGH
Combustible
WALL
NOTE
For Low Profile Enclosure Refer
to Page #11 for installation
instructions.
11.0"
11.0"
5.0" MIN.
For Combustible
Enclosure Top
NOTE!
This UNIT is not
Load Bearing
MIN.
36.0"
FIGURE 1
FIGURE 2
SEE-THROUGH FIREPLACE SHOWN
FIREPLACE ASSEMBLY
1.
Mount Door Cover Figure #2. First apply a
small bead of High Heat Silicone to door seal.
Mount Door and screw into place, making sure that
Door is properly sealed.
2.
Hang Heat Shield on top edge of Fireplace,
and secure with self tapping screws. Heat
Shield must be centered allowing a 1/2"
clearance both sides of Fireplace for
finishing material.
3.
The heat shield and rear
standoff are equipped with
nailing tabs. Level Fireplace and
nail or screw into place.
37.0"
2.5"
6.0"
11.062"
41.125"
20.625"
GAS LINE
R/H UNIT
BOTTOM
ENTRY
2.0" X 3.0"
NOTCH FOR
END GAS
ENTRY
GAS LINE
L/H UNIT
REAR STAND OFFS
COMPLETE WITH
NAILING TABS
DOOR
COVER
HIGH TEMP
SILICONE
NAILING TABS
HEAT
SHIELD
COMPLETE
WITH
NAILING
TABS
NOTE:
Clearance to back of unit
and/or sides of unit framed into walls
require 6” minimum clearance to
combustibles. We recommend using
two (2 x 4) studs placed against the
wall as per framing diagrams. See
Page 3 - Locating your Appliance, for
additional information.