6. Initial operation

6.1 General instructions

Initial operation

Initial operation must be carried out by a qualified expert, with
the direct supplier of the wastewater lifting station responsi-
ble for his availability. During initial operation, a test run with
water is required over at least two switching cycles. During
the test run, dry running must be avoided. Before, during and
after this test run, the following must be checked:
a) The electric fuse protection of the wastewater lifting stati-

on according to IEC or local regulations

b) The direction of rotation of the motor
c) The gate (actuation, open position, air-tightness)
d) The  switching  and  setting  of  switching  heights  in  the

collecting tank, in as far as these are not pre-set by the
manufacturer

e) Air-tightness of the system, fittings and pipes
f) Check on operating voltage and frequency
g) Functional test on the backflow preventer
h) Malfunction warning device
i) Attachment of the pressure pipe
j) Motor protection switch; check by briefly screwing indivi-

dual fuses out (two-phase run)

k) Oil level (if oil chamber exists)
l) Pilot lamps and counters
m) Functional test for any manual pump that may be instal-

led.

Initial operation must be documented in writing, whereby im-
portant data e.g. setting of the motor protection switch and
status of operating hours counter must be noted. 

This initial operation may only be carried out by authorised
specialist staff.

DIN 1986, part 3, must be heeded during the initial operati-
on of lifting stations.

CAUTION:

Before initial operation the inlet pipes and the pumps must
be cleaned of solid materials such as metal, sand etc.

Before initial operation the pump must be filled with pumping
fluid up to the height of the ventilation bore hole of the pump
housing.

The pump must not suck in any air!

After the complete and correct installation of the complete sy-
stem and all the additional parts as well as the pipe and el-
ectrical installations, the system can be put into operation.
Any shut-off valves must be opened.
Make sure before you put the system into operation that the
nominal voltage and type of current specified for the system
correspond to the nominal voltage and type of current on site. 

Check  the  system  installation/cabling  carefully  before  you
put the system into operation. Is the protective earthed con-
ductor  working?  Have  the  relevant  standards/guidelines
been heeded, particularly with a view to the potentially ex-
plosive area?
Do not put the system into operation if there is any damage
to the motor, switch unit or cables visible.
Always follow the safety instructions in chapter 1 of this ma-
nual.

IMPORTANT:

All screw connections must be checked for a tight fit.

6.2 Pressure outlet connecting pieces

The pressure outlet connecting pieces of the lifting stations
are equipped with a backwater flap with aerating device as
standard for each pump. The aerating device must always be
in operating position (see Fig. 1).

The flap (dotted line) is opened exclusively by the pumping
flow of the pump.

6.3 Operating the switch unit (from model year 01/10)

As soon as the network connection has been set up, initiali-
sation takes place immediately, i.e. the system undertakes a
self-test. After  this  test,  the  system  is  ready  for  operation
(mains LED lights up).
The acoustic alarm can be switched off by pressing the alarm
LED. The pump(s) can be switched on manually by pressing
the pump key twice.

Fig. 1

Содержание Aqualift F Standard

Страница 1: ...o Product advantages Simple connection through moulded connecting pieces Drilling surfaces for further connections Fully automatic operation Maintenance friendly PE tank General technical approval no...

Страница 2: ...chgear and the level control are under voltage and may not be opened Only electricians may work on the electrical equipment The term electrician is defined in the VDE 0105 Steps must be taken to ensur...

Страница 3: ...ise level is created that may be a nuisance depending on how the pump is installed If there are maximum noise level stipulations that need to be observed appropriate mea sures need to be taken The sou...

Страница 4: ...6 3 Operating the switch unit Page 18 6 4 Functional description Page 19 6 5 Functional test Page 19 7 Inspection and maintenance 7 1 Notes on the pump Page 20 7 2 Notes on aeration device Page 20 7...

Страница 5: ...entilation pipes at least DN 70 Wearing media must be kept away from the pump im peller The systems are suitable for constant wastewater tempera tures up to 35 C A maximum temperature of 60 C is per m...

Страница 6: ...100 order no 28647 28649 with non return valve DN100 110 DN70 75 DN32 40 DN100 110 475 Zulaufh he 180 3 1 2 Twin system 1 1 kW with pressure outlet DN 100 order no 28652 28659 with non return valve Tw...

Страница 7: ...g 7 x 1 5 mm2 Temperature of material pumped 35 C Weight pump 30 kg 31 kg Protective rating IP 68 24h 3m WS Operating mode S1 S3 Max period of perm operation 240 Min 30 duty cycler Sound level 70 db 7...

Страница 8: ...uit TF1 and TF2 b Up to model year 01 10 Level inputs each 15 8 V input approx 5 mA circuit TF or TF1 and TF2 and E7 or E7 and E8 for connecting the temperatu re switch of the pump motor sensor supply...

Страница 9: ...e system Such dama ge is not covered by the warranty 4 1 Fitting the collecting tank Umaintenance work on the lifting stations they must always be installed in such a way that there is sufficient acce...

Страница 10: ...out using connection clamps or rubber hoses with hose clamps To prevent the high tension forces leading to deformation at the connecting piece a suitable supporting ring must be pus hed into the upper...

Страница 11: ...pumping heights from 5 m Backwater flaps to avoid pressure blows for installation in the IMPORTANT In the case of all the connections drilled at the side it must be remembered that the level control i...

Страница 12: ...nected cables must be strain relieved Screw connections not used must always be sealed properly CAUTION Only qualified electricians may carry out the work on el ectrical equipment described below Befo...

Страница 13: ...d on the right at TF input wire 5 on the left at TF input Input E7 The jumper must be left Level inputs ON ALARM The cable must always be routed rising to the switch unit The cable ends of the pressur...

Страница 14: ...of the relays is prin ted on the board It means malfunction and alarm message is switched on The relay contacts do not have any internal connection to any kind of supply or operating voltages of the...

Страница 15: ...be left Input E8 The jumper must be left Level inputs ON ALARM The cable must always be routed rising to the switch unit The cable ends of the pressure level switch must be connected to the respectiv...

Страница 16: ...ot be used to switch different pha ses The phase may deviate from L1 however The malfunction and warning messages are issued via a relay changeover contact without protective circuit Inductive loads m...

Страница 17: ...off Anti blocking function off OFF up to year 12 09 5 6 Configuration of switch unit up to model year 12 09 Configuration of the control is carried out in the factory using switches S601 S604 between...

Страница 18: ...ch as metal sand etc Before initial operation the pump must be filled with pumping fluid up to the height of the ventilation bore hole of the pump housing The pump must not suck in any air After the c...

Страница 19: ...e other pump is switched on Parallel operation As the soiled water level rises in the tank the level switch on 1 closes After the on 1 switched has closed the switch on delay time begins see section 5...

Страница 20: ...return valve for function if appropriate The backwater flap must be replaced after 2 years of ope ration 7 1 Notes on the pump The pump should be checked at regular intervals If opera tional noises in...

Страница 21: ...the same type The contactor is a wearing part and should be checked and changed if necessary once a year if possible When chan ging the batteries make sure you dispose of them properly with the envir...

Страница 22: ...ed Too little pumping capacity Aeration device not in operating position Wrong direction of rotation for motor In the case of twin systems both motors are rotating the wrong way Reduced capacity throu...

Страница 23: ...ilar Backwater flap faulty wastewater runs out of the pressure pipe back into the system Foam formation in the system Tank or pumps are blocked by grease being discharged in large quantities Level con...

Страница 24: ...ust be acknowledged using the alarm key In the case of lifting stations jumper TF2 faulty not installed Replace install jumper Motor fault Duo Pump 1 Duo Pump 2 Running time limit fault running freque...

Страница 25: ...eck the air hose for leaks Rotary field phase fault Rotary field fault Wrong rotary field for mains connection of switch unit Swap 2 phases Phase fault Phase L1 or L2 L3 not available Check connection...

Страница 26: ...ing excee ded If the alarm level is exceeded both pumps switch on If the level drops below the on 2 level the pumps switch off Non closing on 2 level switch Malfunction message follows the alarm level...

Страница 27: ...ndicates this 8 2 3 Malfunction message SMalfunction messages are sent through Activation of the malfunction relay and thus through the warning device connected to this Display of the type of malfunct...

Страница 28: ...zeige Automatikbetrieb Niveau Anzeige leuchtet Pumpniveau erreicht Pumpen Anzeige leuchtet Pumpe l uft Unterdr cken des akustischen Alarms mit Taste Ausschalten Handbet tigen der Pumpe mit Taste g g g...

Страница 29: ...lfunction Phase rotary field red Permanently lit Phase failure has display priority for information for the Flashing Rotary field fault fitter motor protection Motor protection switch red Motor protec...

Страница 30: ...elec trician must always be consulted The current set at the motor protection switch must corre spond with the rated current of the connected motor and must not be adjusted by the operator Following...

Страница 31: ...31 9 2 2 Switch unit for single system from model year 12 09 9 Control unit Edition 04 99 Du EINZ F...

Страница 32: ...ivated Pump 2 green Pump output 2 activated Malfunction Phase rotary field red Permanently lit Phase failure has display priority for information for the Flashing Rotary field fault fitter motor prote...

Страница 33: ...33 9 3 2 Switch unit for double system Aqualift Duo up to model year 12 09 9 Control unit Edition 04 99 Du DUO F...

Страница 34: ...5 850118 DN 150 850119 Saw cap DN 50 DN 150 50100 Battery 1 unit from model year 01 2010 197 081 Rechargeable battery up to model year 12 2009 20230 Non return valve for mono systems DN 100 28683 Non...

Страница 35: ...mersible pipe 6 1 206 018 Cleaning cover 7a up to 12 09 1 206 048 Mono switch unit 1 1 kW 7a up to 12 09 1 206 116 Mono switch unit 2 2 kW 7b up to 01 10 1 363 100 Mono switch unit 1 1 kW 7b up to 01...

Страница 36: ...7a up to 12 09 1 206 117 Duo switch unit 2 2 kW 400 V 7b from 01 10 1 363 117 Duo switch unit 1 1 kW 400 V 7b from 01 10 1 363 118 Duo switch unit 2 2 kW 400 V 8 1 28663 Pressure hose D 110 x 6 for DN...

Страница 37: ...ingle system 206 017 Pos Unit Part No Description 1 1 28045 Pressure control unit mono 2 1 206 014 Upper part of pressure control unit 3 1 206 045 Cable screw connection 4 5m 206 047 Cable 5 2 017 153...

Страница 38: ...N 100 part no 240 051 Pos Unit Part No Description 1 1 240 046 Flap housing 2 1 240 048 Hose connection 110 3 1 240 038 Hex locknut M8 4 1 240 037 O Ring 5a 1 240 068 Backwater flap for 1 1 kW inc fla...

Страница 39: ...09 T piece DN 100 4a 2 240 068 Backwater flap for 1 1 kW inc flap stay 4b 2 240 069 Backwater flap for 2 2 kW inc flap stay 6 4 240 027 O Ring 7 8 240 058 Hexagon safety screw M6 8 8 240 059 Hexagon s...

Страница 40: ...SEL products are warranted for a period of 24 month This warranty period be gins on the day the product is shipped form KESSEL to its cu stomer The warranty only applies to newly manufactured products...

Страница 41: ...41...

Страница 42: ...erating instructions Initial operation and instruction were not carried out The client person responsible for initial operation was handed the following components and or product components Initial op...

Страница 43: ...______________________________ Contracted plumbing company __________________________________________________________ Address __________________________________________________________ Telephone Fax _...

Страница 44: ...ifting Stations and pumps K Drains and shower channels K Separators Grease Separators Oil Fuel Coalescence Separators Starch Separators Sediment Separators K Septic Systems K Inspection Chambers K Rai...

Отзывы: