5586996-JSG-A-0120 | Start-Up & Operation Guide
Month
Day
Year
Name/Phone
Customer/Contractor Signature:
Form Completed by:
Title:
Request for Start-Up
General Inspection
Completed See Notes
14.
Steam units with humidifier:
a.
Steam control valve, Y type strainer, steam trap, and piping are installed
.............................
b.
Return and discharge air humidity sensors are installed
........................................................
c.
Field wiring to the steam control valve is completed
...............................................................
15.
Air filters are installed correctly and clean
..................................................................................
16.
Shipping bolts have all been removed from the fan assemblies
................................................
17.
Refrigeration system is checked for gross leaks (presence of oil)
.............................................
18.
Terminal screws and wiring connections are checked for tightness
...........................................
19.
Outside and exhaust air hoods are installed in operating position, if applicable
........................
20.
All sensors are properly installed
...............................................................................................
21.
The unit has been air balanced
..................................................................................................
22.
Site is ready for equipment operation
.........................................................................................
23.
The unit was modified by a third party manufacturer (such as Fisen) as specified
....................
Observed Product Deficiencies, Concerns, and Notes
I have inspected the installation of the Johnson Controls Premier rooftop unit and verified the pre start-up checklist is complete
and the unit is ready to be started up by an approved technician.
Verified by:
Date:
With reference to the terms of the above contract, we are requesting the presence of your Johnson Controls Authorized Representative at the
job site on
____ / ____ / ____
to start the system and instruct operating personnel. Please contact:
__________________________________
We understand that the services of the Johnson Controls
Authorized Representative will be furnished in accordance with the contract for a
period of time of not more than _______ consecutive normal working hours, and we agree that a charge of _________ per diem plus travel
expenses will be made to Johnson Controls
if services are required for longer than ________ consecutive normal hours or if repeated calls are
required, through no fault of Johnson Controls.
© 2019 Johnson Controls | 100 JCI Way, York, Pennsylvania USA 17406-8469 | www.johnsoncontrols.com
Subject to change without notice. | Form 5773246-JCL-A-619 | New Release | All rights reserved.
The Smart Equipment logo is a trademark of Johnson Controls in the United States and other countries. It is
a part of the Johnson Controls product portfolio.
8