FOUNDATION DETAILS AND GUIDELINES
A.
Ground base Foundation (RCC/PCC)
Ø
The foundation should be water leveled and at least 300mm above the
ground level to maintain cleanliness and avoid flooding.
Ø
The length and width of the foundation should be at least 600mm to
800 mm more than that of the DG set size i.e. 300mm on each side.
Check the foundation level diagonally as well as across the length and
width.
Ø
Please refer to the foundation drawing attached herewith (page-3).
Ø
A rigid foundation ensures the least vibration. Sand Filling should be
there around the foundation. 18mm rubber matting must be used over
the foundation to minimize the vibration effect and noise leakage.
Ø
Ensure that the foundation to support 1.5times of the total wet weight
of the single generator and 2 times of the total weight for the multiple
generators.
Ø
Please refer to the dimension of DG set for deciding the foundation
length, width and depth.
Note: Please ensure that the foundation should not be made over any
basement, water tank or Sewer Line.
B.
Roof top Installation
Ø
A rooftop installation requires proper planning and the structural
design considerations for dynamic loading.
Ø
The weight of Silent DG set should be on Column and Beam through
proper foundation.
Ø
The RCC foundation should be on the Beam or supported on two
Beams.
Ø
ISMC Channel or MS “I” Section may also be used to cater the load of the
DG set with the canopy. Load of ISMC Channel or MS “I” Section should
be on the column of the building.
Ø
M.S. Sheet is to be provided at the bottom of the base frame of the Silent
DG set for roof top installation.
2
JAKSON & CO.
Содержание JakPower Kirloskar Koel Green EA10 G1
Страница 1: ......
Страница 2: ......
Страница 30: ...26 JAKSON CO BY KIRLOSKAR POWER JAKSON COMPANY 550 13...
Страница 31: ...27 JAKSON CO BY KIRLOSKAR POWER JAKSON COMPANY 550 13...
Страница 35: ...POWER JAKSON CO...
Страница 36: ......