22
The following functions are checked:
Functions
Furnace head test
Furnace head test is in progress.
The furnace head test was successful.
The furnace head test failed. Please note the error message on the
display.
Vacuum test
Vacuum test is in progress.
The vacuum test was successful.
The vacuum test failed. Please note the error message on the display.
IRT test
IRT test is in progress.
The IRT test was successful.
The IRT test failed. Please note the error message on the display.
The following information is displayed:
Information
Temperature calibration
Temperature calibration of the furnace is not required.
Some time has passed since the last calibration. Please conduct a
calibration procedure.
Power supply
The power supply voltage is in the acceptable range.
The power supply is outside the acceptable range.
Software version
The currently installed software version is displayed.
4. Installation and Initial Start-Up
If the self-test was successful, the furnace will automatically display
the home screen.
If the program recognizes a malfunction during the test, a
corresponding error message with the corresponding rectification
information appears in the display.
The acoustic signal and the error message can be acknowledged
with the corresponding buttons.
Press the
[Next]
button to acknowledge the self-test.
Before the first firing, the firing chamber should be
dehumidified using the dehumidification program
(see Chapter 5.4 for details).
Please note that the furnace may require a certain
acclimation time after having been set-up.
Particularly if the furnace was exposed to
considerable temperature changes (water
condensation).