INSTALLATION
BASEPLATE INSPECTION. . . . . . . . . . . . . . . . . . . . . . . . 15
SITE/FOUNDATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
LEVEL BASEPLATE . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Cast Iron/Fabricated Steel . . . . . . . . . . . . . . . . . . . . . . . . 16
Feature Fabricated Steel/API Style. . . . . . . . . . . . . . . . . . . . 17
Baseplate Leveling Worksheet . . . . . . . . . . . . . . . . . . . . . . 18
ALIGNMENT AND ALIGNMENT PROCEDURE . . . . . . . . . . . 19
Alignment Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
Alignment Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
Set Up. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Angular Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Parallel Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Complete Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Alignment Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . 22
GROUT BASEPLATE . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
PIPING. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Suction Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Discharge Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Final Piping Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
!
Equipment that is to be installed in a potentially explosive environment must be done so in accordance with the
following installation instructions.
BASEPLATE INSPECTION
1.
Remove all equipment.
2.
Completely clean the underside of baseplate. It is
sometimes necessary to coat the underside of the
baseplate with an epoxy. This may have been
purchased as an option.
3.
Remove the rust preventative solution from the
machined pads with an appropriate solution.
SITE / FOUNDATION
A pump should be located near the supply of liquid and
have adequate space for operation, maintenance, and
inspection.
Baseplate mounted pumps are normally grouted to a
concrete foundation, which has been poured on a solid
footing. The foundation must be able to
absorb any vibration and to form a permanent, rigid
support for the pumping unit.
The location and size of the foundation bolts are shown on
the outline assembly drawing, provided with the pump data
package.
3298 Family Rev. 4/07
15
3
Содержание Goulds Pumps V 3298
Страница 6: ...6 3298 Family Rev 4 07 ...
Страница 26: ...26 3298 Family Rev 4 07 ...
Страница 32: ...32 3298 Family Rev 4 07 ...
Страница 38: ...38 3298 Family Rev 4 07 ...
Страница 106: ...SP 3298 S Group Frame Mounted Sizes 1 x 11 2 6 2 x 3 6 106 3298 Family Rev 4 07 SP3298 S Group Frame Mounted Version ...
Страница 112: ...112 3298 Family Rev 4 07 ...
Страница 115: ...3298 Family Rev 4 07 115 7 ...
Страница 116: ...INTERCHANGEABILITY 3298 XS GROUP 116 3298 Family Rev 4 07 ...
Страница 117: ...INTERCHANGEABILITY 3298 S GROUP 3298 Family Rev 4 07 117 7 ...
Страница 118: ...INTERCHANGEABILITY 3298 M GROUP INTERCHANGEABILITY 3298 M GROUP SIZE 1 x 3 8 ONLY 118 3298 Family Rev 4 07 ...
Страница 119: ...INTERCHANGEABILITY 3298 L GROUP 3298 Family Rev 4 07 119 7 ...
Страница 120: ...INTERCHANGEABILITY SP 3298 S GROUP 120 3298 Family Rev 4 07 ...
Страница 121: ...INTERCHANGEABILITY V 3298 S GROUP 3298 Family Rev 4 07 121 7 ...
Страница 122: ...INTERCHANGEABILITY V 3298 M GROUP 122 3298 Family Rev 4 07 ...
Страница 124: ...124 3298 Family Rev 4 07 ...
Страница 125: ...APPENDIX I 3298 HYDRAULIC COVERAGE CHARTS 3298 Family Rev 4 07 125 8 ...
Страница 126: ...3298 HYDRAULIC COVERAGE CHARTS 126 3298 Family Rev 4 07 ...
Страница 127: ...SP 3298 HYDRAULIC COVERAGE CHARTS 3298 Family Rev 4 07 127 8 ...
Страница 128: ...SP 3298 HYDRAULIC COVERAGE CHARTS 128 3298 Family Rev 4 07 ...
Страница 129: ...V 3298 HYDRAULIC COVERAGE CHARTS 3298 Family Rev 4 07 129 8 ...
Страница 130: ...V 3298 HYDRAULIC COVERAGE CHARTS 130 3298 Family Rev 4 07 ...
Страница 134: ...134 3298 Family Rev 4 07 ...
Страница 136: ...IMPELLER TRIM PROCEDURE 136 3298 Family Rev 4 07 Fig III 2 Group S M Fig III 3 Group L ...
Страница 142: ...142 3298 Family Rev 4 07 ...