Turned tool changing station SK11 and SK20
11
/
27
April 2019
4.1.2
SK 20 assembly
Figure 3: SK20 fastening
4.2
Establishing connections
Attention! Switch off the mains voltage and pull out the mains plug before
connecting the tool changer! Shut off the compressed air and ensure the
absence of pressure!
Only authorised, qualified experts may carry out work on the electrical
equipment of the machine. After completion of the integration of the
turned tool changing station and prior to the initial commissioning, the
machine must undergo inspection in accordance with EN 60204-1:2006,
section 18.7. Route the cable without crossing other high-voltage cables.
Avoid sharp bends and corners when routing the cable and ensure that the
cable is not pinched and cannot be damaged as a result of movements of
the machine. Only use suitable cable guidance systems.
Fasten all six fastening points on the turned changer to the
mounting area of your machine with machine screws (not included
in the scope of supply) and ensure that it is flat and level.
Attention: The turned changer must be positioned in the
travel range of your CNC machine.