Precedent Units Step 2 - Antenna and Battery Installation
Antenna Installation and Cable Routing
1. Open all unit doors and access panels.
2. Mount the antenna to the antenna bracket with the provided washer and
nut and tighten to 10 N•m (88 in-lbs.) The antenna is non-directional
and can be mounted in any direction.
3. Attach the antenna bracket to the frame with the supplied M6 screw
and tighten hardware to 6.49 N•m (4.79 ft-lb.). There is a single insert
provided in the frame for this bracket.
4. Route the antenna cable to the control box as shown.
•
Secure the cable to the main harness with bandwraps.
•
Route the cable into the control box through the access grommet.
•
Maintain 76.2 mm (3.00 in.) of clearances from the muffler, belts
and pulleys.
•
Cables will be connected to the REB in a later step.
Battery Installation and Harness Routing
5. Place the battery onto the battery bracket mounting studs and secure
with the four supplied M5 flat washers and M5 locking nuts. Tighten
hardware securely.
6. Install the battery and bracket onto the curbside frame channels with
the three supplied M6 screws as shown. Tighten hardware securely.
There are three inserts provided in the frame for this bracket.
NOTE: If your unit has standby power, you will need to remove the
mounting bolts securing the transformer box, install battery back-up
bracket onto the frame and then reinstall the transformer box on top
of the battery back-up bracket and tighten hardware securely.
7. Connect the battery harness to the battery assembly and route the
harness through the frame grommets, along the main harness, and into
the control box.
•
Harness will be connected to the REB in a later step.
8. Attach the supplied warning label to the front door next to the door
latch.
Содержание Thermo King TracKing
Страница 2: ......
Страница 4: ...2 TracKing Cellular Release History Released 07 15...
Страница 13: ...11 Precedent Units Step 2 Antenna and Battery Installation...
Страница 15: ...13 Precedent Units Step 3 REB Installation...
Страница 17: ...15 Precedent Units Step 4 Door Switch Option...
Страница 19: ...17 Precedent Units Step 5 Fuel Level Option...
Страница 23: ...21 SB Units Step 1 Datalogger Configuration Procedures Text Header...
Страница 27: ...25 SB Units Step 3 REB and Battery Installation...
Страница 29: ...27 SB Units Step 3a REB and Battery Installation SR2 to SR3...
Страница 31: ...29 SB Units Step 3b Units with SR2 or SR3 w Razor...
Страница 33: ...31 SB Units Step 3c For Units with ThermoGuard non SR2...
Страница 35: ...33 Super II Units Step 1 Datalogger Configuration Procedures Text Header...
Страница 37: ...35 Super II Units Step 2 Antenna Installation...
Страница 39: ...37 Super II Units Step 3 TracKing Installation...
Страница 44: ...42 BLANK PAGE...
Страница 46: ......