2-2
Chapter 2: Hardware installation
2.2
Installation procedures
This section details the installation procedures of the system, its components, and connections between
equipment. The installation procedures in this section are in order, so it is strongly recommended
that you follow the said order to reduce the time consumed during installation and prevent installation
mistakes, technical mishaps, or physical injuries.
2.2.1 Unpacking the system
When your system package has arrived, check and confirm if the contents of your package are complete
by referring to the
Unpacking List
document, which is bundled with in your package.
Accessory box contents
This box contains the following:
•
RS-232C serial cable (mini USB to DB-9 cable)
•
Screws (for 2.5 and 3.5 inch drives)
•
Quick installation guide
•
EonOne Quick Start Guide
•
EonOne CD
•
LAN cable
•
Power cord
Pre-installed components
Below are the components that are pre-installed in the system:
•
LED front panels
•
DIMM modules
•
M.2 flash module
•
Drive trays
Components that need user installation upon unpacking
You must do the following installation:
•
Assembling the drives to the drive trays
•
Installing the host/expansion board to the system
•
Cabling in between systems
2.2.2 Preparing for the installation
Before you start the system installation, you must prepare the following:
•
1 Small-sized flat blade screwdriver
•
2.5-inch or 3.5 inch disk drives (supports up to 3 TB each drive)