BOILER COMMISSIONING
(INITIAL CHECK)
To commission the boiler:
- ensure that the type of gas used corresponds to
boiler settings;
- check connection to a 230V-50Hz power
mains, correct L-N polarity and the earthing
connection;
- make sure the heating system is filled with
water and that the manometer indicates a
pressure of 1 - 1.2 bar;
- make sure the air valve cap is open and that the
system is well deaerated;
- switch the boiler on and ensure correct ignition;
- make sure the gas maximum, medium and
minimum flow rate and pressure values
correspond to those given in the handbook
(Par. 3.16);
- check activation of the safety device in the event
of no gas, as well as the relative activation time;
- check activation of the master switch located
upstream from the boiler and in the boiler;
- check the existing draught during normal
functioning of the appliance, e.g. a draught
gauge positioned at the exit of the appliance
combustion products;
- check that there is no backflow of combustion
products into the room, even during
functioning of fans;
3.1 HYDRAULIC LAYOUT.
Key:
1 - Gas valve
2 - Stainless steel coil for boiler
3 - Magnesium anode
4 - Stainless steel boiler
5 - Air bleeding valve
6 - Burner
7 - Combustion chamber
8 - Primary heat exchanger
9 - Fumes hood
10 - Flue safety thermostat
11 - Delivery probe
12 - Safety thermostat
13 - System expansion tank
14 - Boiler circulating pump
15 - Adjustable by-pass
16 - System drain cock
17 - 3-way valve (motorised)
18 - Domestic water probe
19 - 3 bar safety valve
20 - System filling cock
21 - 8 bar safety valve
22 - Cold water inlet non-return valve
23 - Boiler drain cock
G - Gas supply
AC - Domestic hot water outlet
AF - Domestic cold water inlet
R - System return
M - System delivery
- ensure activation of all adjustment devices;
- seal the gas flow rate regulation devices (if
settings are modified);
- ensure production of hot domestic water;
- ensure sealing efficiency of water circuits;
- check ventilation and/or aeration of the
installation room where provided.
If any checks/inspection give negative results, do
not start the boiler.