Installation
17
INSULATING CASING ASSEMBLY
To fit the insulating casing proceed as follows:
–
wrap the heat insulating mat around the boiler body and fasten it with the supplied strap (1)
–
prepare the slats (2) inserting the locking plugs (3) in the corners of each one of them, as shown in the figure below
1
2
3
–
fasten the uprights and the crosspieces (4) to the plates (5) with the screws and nuts supplied as standard
m
IMPORTANT
the crosspiece (6), if included in the package, must be positioned between the two square pipes to support the slats.
5
4
4
5
6
–
insert the slats (2), previously prepared with locking plugs, between the uprights and the crosspieces, as in the figure.
Leave
the upper corner uncovered on the pockets side for the following installation of the control panel with the relevant bulbs
–
after completing the installation of the slats and the fastening of the central templates (7), fasten the closing profile (8) with
the self-tapping screws supplied as standard
2
2
8
7
Cooke Industries - Phone: +64 9 579 2185 Email: [email protected] Web: www.cookeindustries.co.nz