AST0922-940
Page
5
INSTALLATION
OF
IBC CABINET WATER SOFTENER UNIT
FITTED WITH MODEL 255 VALVE/940 CONTROL
Check the equipment upon arrival for damage or shortages and report same to our Office or
Agent before starting.
Position the Softener Cabinet on a firm foundation, preferably concrete, with sufficient space
for operation and maintenance.
STEP 1
Connect inlet, outlet pipes and drain line to control valve as per Instruction
Booklet (page 5, figure 3).
Note
: The softener is supplied with the Autotrol Series 156 Bypass Valve as
standard.
STEP 2
Remove lid from brine tank. Then connect brine overflow drain line to waste
trap.
STEP 3
Refer to Instruction Booklet for start up procedure (page 6 “Placing conditioner
into Service”).
STEP 4
Load recommended quantity of water softener salt into brine tank and replace
lid (refer to Table 3 “Brine Tank Salt Loading”).
Table 3
MODEL
RESIN LITRES
BRINE TANK - SALT
LOADING KG
AST0922-940
22
50
Содержание AST0922-940
Страница 20: ...AST0922 940 Page 20 Control Valving Identification Valve Disc Operation...
Страница 21: ...AST0922 940 Page 21 Flow Diagrams...
Страница 22: ...AST0922 940 Page 22...
Страница 24: ...AST0922 940 Page 24...
Страница 25: ...AST0922 940 Page 25 Valve Body and Tank Adaptor Module...
Страница 29: ...AST0922 940 Page 29...