(1) Cable tie
(2) Label
(3) Cable
2.
Bind the label to the cable, as shown in
. Cut off the surplus part of each cable
tie.
Figure 3-29
Binding the label to the cable
(1) Cable tie
(2) Cable
(3) Label
NOTE
Ensure that the labels are arranged in an orderly and neat manner and the cable ties are installed in
the same direction. An extra length ranging from 3 mm to 5 mm should be left for each cable tie.
3.2 Procedure for Installing the RRU and SRXU
The procedure for installing the RRU and SRXU varies with the installation scenarios. The
procedure involves making preparations, installing the RRU and SRXU, connecting related
cables, checking the hardware installation, and installing the housing of the RRU and SRXU.
Context
CAUTION
After the NodeB is installed, it must be powered on within 48 hours.
NOTE
Contact Huawei engineers for confirmation if:
l
You choose to prepare the devices, cables, and connectors by yourself.
l
You need to shorten the cable of a specified length.
Procedure
Step 1
Unpack the RRU and SRXU, check the items in the package, and prepare tools and instruments.
Step 2
Install the RRU. The installation mode of the RRU varies with the installation scenarios.
3 Installing RRU and SRXU Hardware
RRU
User Guide
3-26