<HUAWEI>
display dustproof
Clean Dustproof-Net cycle : 365(days)
Last clean date : 2011/02/07
Up to last clean days : 1(day)
Clean alarm existence days: 0(day)
1.6 Configuration Examples
This section provides several examples for maintaining the router.
1.6.1 Example for Powering Off the MPU
When the MPU fails or needs maintenance or a hardware upgrade, you need to power off the
board. Then, you can remove the board.
Networking Requirements
After checking the alarm information, you find that the hardware on the master MPU fails. Then,
power off the master MPU and check it.
Configuration Notes
CAUTION
On a single NE5000E, interfaces are numbered in the format of slot number/sub-card number/
interface number; whereas in the multi-chassis scenario, interfaces are numbered in the format
of chassis ID/slot number/card number/interface number. This requires the chassis ID to be
specified along with the slot number.
The NE5000E cannot work with a single MPU for a long time. If the MPU fails, the whole
system is broken down. After the slave MPU is powered off, you must finish required operations
and restore the MPU immediately.
Configuration Roadmap
The configuration roadmap is as follows:
1.
Switch the master MPU to the slave MPU.
2.
Power off the slave MPU.
Data Preparation
To complete the configuration, you need the following data:
l
Slot number of the master MPU
Procedure
Step 1
Perform a master/slave switchover on the router.
<HUAWEI>
system-view
[~HUAWEI]
slave switchover
HUAWEI NetEngine5000E Core Router
Configuration Guide - System Management
1 Device Management
Issue 01 (2011-10-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
11