![Huawei FusionModule500 Скачать руководство пользователя страница 147](http://html.mh-extra.com/html/huawei/fusionmodule500/fusionmodule500_user-manual_168046147.webp)
4.3.3.1.1 Cable Routing Description
Figure 4-103 Holes for routing cables through the top of the cabinet
(1) Holes for pipes of smart
cooling products
(2) Signal cable holes
(3) Input power cable holes
Wire bushings are installed at the cable outlets of the cabinet for ease of cable
routing. Cut a cross in the middle of a wire bushing using an electrician's knife, as
shown in
.
Figure 4-104 Cutting a cross in a wire bushing
Cables can be bound to the side panels and mounting bars of the cabinet.
FusionModule500 Smart Mini Data Center
User Manual
4 Installation Guide
Issue 02 (2020-12-25)
Copyright © Huawei Technologies Co., Ltd.
137